As of September 30, 2002

Physical Progress

Contractor

Matsushita - Itochu Consortium

Commencement of the Works

13 March 2002

Contract period 1080 days (Until March 12, 2005)
Time Elapsed (days) 558 of 1080 (51.67%) Remaining 522 days

Progress

 
  - Start the excavation work for foundation of Ventilation Adit Building

Photographs

Start Excavation for Foundation of Ventilation Adit Building
Full View of VAB Site (September 23)
Formwork and Rock Bed for Lean Concrete at Ventilation Adit Building
Preparation for Lean Concrete at Ventilation Adit Building
Lean Concrete Placing for Foundation of Ventilation Adit Building (September 30)
Sampling for testing (September 30)
Materials on Site (September 13)
Sampling (September 17)
Measurement for Test (September 23)
Tensile test (September 23)

Top

Construction Supervision

Summary

Water Supply and Treatment System

- Backfill for High Level Reservoir completed.

- Storage places for materials at both north and south portals are completed.

- Piping materials for main tunnel are delivered to warehouses.

Tunnel Ventilation System

- Shop drawings for machinery of Ventilation System are approved.

- Shop drawings for EP stations are being prepared.

Ventilation adit building

- Excavation for foundation started.

- Lean concrete for two footings was placed.

Top

Previous month / Next month

This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination