Welcome to Our Site!
 

As of October 31, 2002

Physical Progress

Contractor

Matsushita - Itochu Consortium

Commencement of the Works

13 March 2002

Contract period 1080 days (Until March 12, 2005)
Time Elapsed (days) 588 of 1080 (54.44%) Remaining 492 days

Progress

 
  Start anchoring work for piping installation for water supply and treatment system in the main tunnel and survey work for EP No.1 for Tunnel Ventilation System.

Photographs

Lean Concrete Placing for Ventilation Adit Building
Survey work for EP No.1 for Tunnel Ventilation System
EP Control Panel
Function Test for EP Fan Local Operation Panel

Top

Construction Supervision

Summary

Permanent work

Water Supply and Treatment System

- Supports for water pipes in the main tunnel were anchored.

- Prepared Piping materials for main tunnel

Tunnel Ventilation System

- Joint inspection for taking over of EP No.1 was conducted together with PKIA, PK3 and PK4 in the presence of the Engineer on Oct. 10 and EP No.3 on Oct. 30.

- Completed the survey and marking work for EP No.1 and prepared work drawings.

Ventilation Adit Building

- Lean concrete was placed for 14 footings

- Concrete tests after 7 days and 28 days of curing was conducted.

Joint Inspection for taking over of cable conduit PKIA, PK3, PK4 on October 23 and 30 for Zone P (South) and October 29 for Zone A, B (North).

Top

Previous month / Next month

This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination