As of August 31, 2002

Physical Progress

Contractor

Matsushita - Itochu Consortium

Commencement of the Works

13 March 2002

Contract period 1080 days (Until March 12, 2005)
Time Elapsed (days) 528 of 1080 (48.88%) Remaining 552 days

Progress

 
 

- Complete the backfill for High Level Reservoir and installation of water pipes and signal cable conduit at OCC building

Photographs

Backfill for High level reservoir - The area where backfill is placed (Aug. 5)
Backfill for High level reservoir - Inspection of 8th layer (Aug. 16)
Backfill for High level reservoir - Compaction test
Backfill for High level reservoir - 16th layer, backfill completed (Aug. 29)
Backfill for High level reservoir - Installation of signal cable conduit (Aug. 12)
Backfill for High level reservoir - Installed water pipes (Aug. 25)

Top

Construction Supervision

Summary

Shop drawings for machinery of Ventilation System were approved.

Measurement work for Ventilation Adit Building were completed.

Regarding the construction of High Level Reservoir, backfill was completed and the installation of water pipes and signal cable conduit at OCC building was executed.

One third of materials for Water Treatment System was imported.

Storage areas at North and South Portal was under construction

Top

Previous month / Next month

This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination