As of July 31, 2002

Physical Progress

Contractor

Matsushita - Itochu Consortium

Commencement of the Works

13 March 2002

Contract period 1080 days (Until March 12, 2005)
Time Elapsed (days) 502 of 1080 (46.46%) Remaining 578 days

Progress

 
 

- Complete the design of foundation at Ventilation Adit Building.

- Site of backfill handed over for High Level Reservoir.

Photographs

Compaction before backfill
Compaction before backfill

Top

Construction Supervision

Summary

Preparation of shop drawings for approval achieves about 70%

Design of Ventilation Adit Building foundation was completed and submitted for approval.

Necessary arrangement of Ventilation backfill for High Level Reservoir was made.

Import of materials for Water Treatment System is started.

Fabrication of fan ducts in Vietnam comes to the finishing stage.

Permanent Works:

Design of foundation for Ventilation Adit Building completed 5.7%

Site of backfill at High Level Reservoir handed over 4.8%

Top

Previous month / Next month

This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination