Progress Report > Package IV - Mechanical Works
Summary Shop drawings for various fans are approved. Shop drawings for EP Systems and auxiliary equipment are approved Shop drawings and specifications for Panels and Ventilation Control System submitted for approval. Invest boring for Ventilation Adit Building is completed.Permanent Works: