As of May 31, 2002

Physical Progress

Contractor

Matsushita - Itochu Consortium

Commencement of the Works

13 March 2002

Contract period 1080 days (Until March 12, 2005)
Time Elapsed (days) 442 of 1080 (40.92%) Remaining 638 days

Progress

 
 

- Design water system and ventilation system.

- Manufacture the ventilation fans.

Photographs

Getting Samples Out From Bore Hole 2 (May 26, 2003)
Drilling Bore Hole 1 (May 28, 2003)
Demobilization of Equipment (May 31, 2003)
Samples Taken Out From Bore Hole 1 (May 28, 2003)

Top

Construction Supervision

Summary

Studied work schedule in accordance with the revised work schedule of the civil contractors.

Finalize the layout arrangement of cable conduit and pit in coordination with the related contractors.

Discuss on necessary arrangement for investigation boring and work schedule of Ventilation Adit.

Review the design of high level reservoir for preparing shop drawings of approval.

Discuss the outstanding matters with PK3

Study the oversea study tourand factory acceptance test for the year 2003.

Construction of site office and warehouse completed.

Apply for the Import License.

Permanent Works:

Shop drawings for various fans were approved.

Shop drawings for EP systems and auxiliary equipment have been approved.

Procurement of materials for Water supply/treatment system and manufacturing of ventilation equipment are in progress.

Temporary Works

The Construction work of the site office and warehouse was completed.

Top

Previous month / Next month

This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination