Progress Report > Package IV - Mechanical Works
Summary Studied work schedule in accordance with the revised work schedule of the civil contractors. Finalize the layout arrangement of cable conduit and pit in coordination with the related contractors. Discuss on necessary arrangement for investigation boring and work schedule of Ventilation Adit. Review the design of high level reservoir for preparing shop drawings of approval. Discuss the outstanding matters with PK3 Study the oversea study tourand factory acceptance test for the year 2003. Construction of site office and warehouse completed. Apply for the Import License.Previous