As of September 30, 2003

Physical Progress

Contractor

JV of Dong Ah and Song Da

Commencement of the Works

1st October 2000

Contract Period

1460 days (Until September 30, 2004)

Time Elapsed (days)

1080 of 1460 (73.97%) Remaining 380days

Progress

 

Main Tunnel(2417m)

Excavated 2379m in total (100%)

Evacuation Tunnel(2429m)

Excavated 2411m in total (100%)

Access Road to Water Reservoir.

Completed

Bridge No.1(58m)

58m (2 nos.) of girders casted in this month

Others

 

 

Photographs

South Tunnel Portal Area - September 2003
Drilling of Face for Main Tunnel
Inspection of Double Welding Connection
Carrying out the Nailshot for Geotextile
Placement of Concrete Electric - Cable Duct
Construction of Center Drainage
Construction of Center Drainage
Embankment of Sub-base for Main Tunnel
Construction of Cross Passage No.7
Embankment of Sub-base Layer for E.P
Drilling of Face for Evacuation Tunnel
Testing Sample for Concrete Lining

Top

Construction Supervision

Summary

Main Tunnel top heading and Evacuation tunnel to contract limit @ 5+500 is complete (100%).  PKIB continue excavation beyond Sta. 5+500 as subcontractor to PKIA contractor.

During the reporting period 110.7m of Evacuation Tunnel and 115.9m of Main Tunnel Top Heading was excavated, giving a total length of 2680.9m of Evacuation Tunnel and 2781.5m of Main Tunnel Top Heading excavated to date.

Bench excavation continued with 32.6m excavated on the East Side.

Tunnel lining continued with 210.7m of main tunnel, 12.4m of layby completed.

Work continued on Electrostatic Precipitator No. 3, the centre drain, earthing and aggregate base course were completed.

Main Tunnel

A total of 115.9m of Main Tunnel Top Heading was excavated over the reporting period, giving a total length of 2781.5m of Main Tunnel Top Heading excavated to date.

Face No.7

 – 115.9m of Top Heading excavated from 2+665.6 to Sta. 2+781.5

Bench excavation

– 32.6m of bench excavated from St. 2+227 to St. 2+259.6 (East side)

Tunnel Lining

Concrete for Foundation Beam –92.3m Fr. St. 2+110.2 to Sta. 2+202.5  (West Side)

Concrete for Foundation Beam –25.7m Fr. St. 2+ 157.6 to Sta. 2+201.3 (East Side)

                    Total quantity                                               50.2 m3

Concrete for Tunnel Lining – 210.7m (18 blocks) from St. 6+027.5 to Sta. 6+015.5 and Sta. 5+894.5 to Sta. 5+785.6

                    Total quantity                                               3146m3

            Installation of mole drain                            150m

            Installation of waterproof membrane                  160m

            Placement of concrete for side drain

                                                244.6m (East side)

                                                714.7m (West side)

            Placement of concrete for cable trough (West side)            336.5m

            Placement of concrete for construction of centre drain 95m

Evacuation Tunnel

A total of 110.7m of Evacuation Tunnel was excavated from St. 2+570.3 to Sta. 2+680.7 over the reporting period. Giving a total length of 2680.9m of tunnel excavated to date.

Bridge No. 1

66m (2 No.) of girder cast

Major Events and Issues

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination