Progress Report > Package IB - South Tunnel Section
Main Tunnel top heading and Evacuation tunnel to contract limit @ 5+500 is complete (100%). PKIB continue excavation beyond Sta. 5+500 as subcontractor to PKIA contractor. During the reporting period 110.7m of Evacuation Tunnel and 115.9m of Main Tunnel Top Heading was excavated, giving a total length of 2680.9m of Evacuation Tunnel and 2781.5m of Main Tunnel Top Heading excavated to date. Bench excavation continued with 32.6m excavated on the East Side. Tunnel lining continued with 210.7m of main tunnel, 12.4m of layby completed. Work continued on Electrostatic Precipitator No. 3, the centre drain, earthing and aggregate base course were completed. Main Tunnel A total of 115.9m of Main Tunnel Top Heading was excavated over the reporting period, giving a total length of 2781.5m of Main Tunnel Top Heading excavated to date. Face No.7
Bench excavation
Tunnel Lining Concrete for Foundation Beam –92.3m Fr. St. 2+110.2 to Sta. 2+202.5 (West Side) Concrete for Foundation Beam –25.7m Fr. St. 2+ 157.6 to Sta. 2+201.3 (East Side) Total quantity 50.2 m3 Concrete for Tunnel Lining – 210.7m (18 blocks) from St. 6+027.5 to Sta. 6+015.5 and Sta. 5+894.5 to Sta. 5+785.6 Total quantity 3146m3 Installation of mole drain 150m Installation of waterproof membrane 160m Placement of concrete for side drain 244.6m (East side) 714.7m (West side) Placement of concrete for cable trough (West side) 336.5m Placement of concrete for construction of centre drain 95m Evacuation Tunnel A total of 110.7m of Evacuation Tunnel was excavated from St. 2+570.3 to Sta. 2+680.7 over the reporting period. Giving a total length of 2680.9m of tunnel excavated to date. Bridge No. 1 66m (2 No.) of girder cast Major Events and Issues This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||||||||||