As of August 31, 2003

Physical Progress

Contractor

JV of Dong Ah and Song Da

Commencement of the Works

1st October 2000

Contract Period

1460 days (Until September 30, 2004)

Time Elapsed (days)

1050 of 1460 (71.91%) Remaining 410days

Progress

 

Main Tunnel(2417m)

Excavated 2379m in total (100%)

Evacuation Tunnel(2429m)

Excavated 2411m in total (100%)

Access Road to Water Reservoir.

Completed

Bridge No.1(58m)

58m (2 nos.) of girders casted in this month

Others

 

 

Photographs

South Tunnel Portal Area
Installation of Reinfocement Steel for Walk for Pedestrian of West
Place of Concrete for Side Drain of West
Construction of subbase for walkway
Inspection of Double Welding Connection
Placement of Concrete Lining for Layby
Placement of Concrete Lining for Main Tunnel
Drilling of Face for Main Tunnel
Drilling of Face for Evacuation Tunnel
Construction of Bridge No.1
Testing sample for concrete lining
Drilling Core for Checking Thickness of Support Shotcrete

Top

Construction Supervision

Summary

Main Tunnel top heading and Evacuation tunnel to contract limit @ 5+500 is complete (100%).  PKIB continue excavation beyond Sta. 5+500 as subcontractor to PKIA contractor.

During the reporting period 94.9m of Evacuation Tunnel and 132.8m of Main Tunnel Top Heading was excavated, giving a total length of 2570.3m of Evacuation Tunnel and 2665.6m of Main Tunnel Top Heading excavated to date.

Bench excavation continued with 45.2m being excavated on the West Side and 93.2m excavated on the East Side.

Tunnel lining continued with 160.8m of main tunnel, 43.4m of layby and 40.9m of Electrostatic Precipitator completed.  The lining of the EP is now 100% completed.

Work continued on the Evacuation Tunnel cut and cover section, concrete arch completed.

Overall a reasonable months progress, slightly up in the main tunnel excavation, but down around 20% in the Evacuation Tunnel.

Main Tunnel

A total of 132.8m of Main Tunnel Top Heading was excavated over the reporting period, giving a total length of 2665.6m of Main Tunnel Top Heading excavated to date.

Face No.7

 – 132.8m of Top Heading excavated from 2+532.8 to Sta. 2+665.6

Bench excavation           

– 42.5m of bench excavated from St. 2+184 to Sta. 2+229.2 (West side)

– 93.2m of bench excavated from St. 2+133.8 to St. 2+227 (East side)

Tunnel Lining

Concrete for Foundation Beam –42.2m Fr. St. 2+068 to Sta. 2+211  (West Side)

Concrete for Foundation Beam –93.2m Fr. St. 1+ 989.4 to Sta. 2+175.6 (East Side)

                    Total quantity                                               95 m3

Concrete for Tunnel Lining – 162.8m (14 blocks) from St. 6+190.2 to Sta. 2+027.5

Concrete Lining of layby 43.2m (8 blocks)

Concrete lining for EP 40.3m (8 blocks)

                    Total quantity                                               3234m3

          Installation of mole drain                      240.5m

          Installation of waterproof membrane           234m

          Placement of concrete for side drain            512.8m (East side)

                                                                      451.4m (West side)

Evacuation Tunnel

A total of 94.9m of Evacuation Tunnel was excavated from St. 2+475.4 to Sta. 2+570.3 over the reporting period. Giving a total length of 2570.3m of tunnel excavated to date.

Cut and cover section:

Poured 338m3 on type B concrete for tunnel arch.

Bridge No. 1

58m (2 No.) of girder cast

Major Events and Issues

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination