Progress Report > Package IB - South Tunnel Section
Main Tunnel top heading and Evacuation tunnel to contract limit @ 5+500 is complete (100%). PKIB continue excavation beyond Sta. 5+500 as subcontractor to PKIA contractor. During the reporting period 94.9m of Evacuation Tunnel and 132.8m of Main Tunnel Top Heading was excavated, giving a total length of 2570.3m of Evacuation Tunnel and 2665.6m of Main Tunnel Top Heading excavated to date. Bench excavation continued with 45.2m being excavated on the West Side and 93.2m excavated on the East Side. Tunnel lining continued with 160.8m of main tunnel, 43.4m of layby and 40.9m of Electrostatic Precipitator completed. The lining of the EP is now 100% completed. Work continued on the Evacuation Tunnel cut and cover section, concrete arch completed. Overall a reasonable months progress, slightly up in the main tunnel excavation, but down around 20% in the Evacuation Tunnel. Main Tunnel A total of 132.8m of Main Tunnel Top Heading was excavated over the reporting period, giving a total length of 2665.6m of Main Tunnel Top Heading excavated to date. Face No.7
Bench excavation
Tunnel Lining Concrete for Foundation Beam –42.2m Fr. St. 2+068 to Sta. 2+211 (West Side) Concrete for Foundation Beam –93.2m Fr. St. 1+ 989.4 to Sta. 2+175.6 (East Side) Total quantity 95 m3 Concrete for Tunnel Lining – 162.8m (14 blocks) from St. 6+190.2 to Sta. 2+027.5 Concrete Lining of layby 43.2m (8 blocks) Concrete lining for EP 40.3m (8 blocks) Total quantity 3234m3 Installation of mole drain 240.5m Installation of waterproof membrane 234m Placement of concrete for side drain 512.8m (East side) 451.4m (West side) Evacuation Tunnel A
total of 94.9m of Evacuation Tunnel was excavated from
St. 2+475.4 to Sta. 2+570.3 over the reporting period.
Giving a total length of 2570.3m of tunnel excavated to
date. Cut and cover section:
Bridge No. 1 58m (2 No.) of girder cast Major Events and Issues This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||||||||||