As of July 31, 2003

Physical Progress

Contractor

JV of Dong Ah and Song Da

Commencement of the Works

1st October 2000

Contract Period

1460 days (Until September 30, 2004)

Time Elapsed (days)

1026 of 1460 (70.27%) Remaining 434days

Progress

 

Main Tunnel(2417m)

136.1m in this month; 2532.8m in total (106.46%)

Evacuation Tunnel(2429m)

96.1m in this month; 2475.4m in total (102.67%)

Access Road to Water Reservoir.

Completed

Bridge No.1(58m)

75m of girder casted

Others

 

 

Photographs

South Tunnel Portal - July 2003
Placement of Concrete for East Walkway
Installation of Formwork for West Side Drain
Compaction of Subbase Layer for Foundation of West Side-Drain
Placement of Concrete for Foundation Beam
Inspection of Double Welding Connection
Placement of Concrete Lining for Main Tunnel
Construction of Bench
Drilling of Face for Main Tunnel
Construction of Cut & Cover of Evacuation Tunnel
Installation of Reiforcement Steel for Cut & Cover of E.T. Portal
Drilling of Face for Evacuation Tunnel
Construction of Bridge No.1
Drilling Cores for Checking Thickness of Support Shotcrete
PMU's guest delegation

Top

Construction Supervision

Summary

During the reporting period 96.1m of Evacuation Tunnel and 136.1m of Main Tunnel Top Heading was excavated, giving a total length of 2475.4m of Evacuation Tunnel and 2532.8m of Main Tunnel Top Heading excavated to date.

Bench excavation continued with 136.1m being excavated on the West Side and 256.4m excavated on the East Side.

Tunnel lining continued with 42.3m of main tunnel, 43.4m of layby and 69.5m of Electrostatic Precipitator completed.

Work continued on the Evacuation Tunnel cut and cover section.

Overall a good months progress, slightly up in the main tunnel excavation, but down around 20% in the Evacuation Tunnel.

Package IB has now passed the PKIA/IB boundary and Dong Ah – Song Da JV continue to excavate as a subcontractor for Package IA.

Main Tunnel

A total of 136.1m of Main Tunnel Top Heading was excavated over the reporting period, giving a total length of 2532.8m of Main Tunnel Top Heading excavated to date.

Face No.7 

– 136.1m of Top Heading excavated from St. 2+396.7 to St. 2+532.8

Bench excavation     

– 172m of bench excavated from St. 2+012 to St. 2+184 (West side)

– 84.4m of bench excavated from St. 1+905.6 to St. 1+1990 and 126.5m from St. 2+007.3 to St. 2+133.8 (East side)

The large geological overbreak between St. 2+119.5 and St. 2+124.5 was backfilled with concrete.

Tunnel Lining

Concrete for Foundation Beam 

–289.1m Fr. St. 1+778.9 to St. 2+068   (West Side)

Concrete for Foundation Beam 

–141.2m Fr. St. 1+ 848.2 to St. 1+989.4 (East Side)

Concrete for Tunnel Lining 

– 42.3m (1 block) from St. 6+232.5 to St. 6+190.2

Concrete Lining of layby 43.4m (8 blocks)

Concrete lining for EP 69.5m (13 blocks)

Backfill grouting of tunnel lining from block 65-122

            Cement quantity                                         8880 kg

            Installation of mole drain                              94m

            Installation of waterproof membrane              136m

            Placement of concrete for walkways

                                                660m (East side)

                                                100m (West side)

Evacuation Tunnel

A total of 96.1m of Evacuation Tunnel was excavated from St. 2+379.3 to Sta. 2+475.4 over the reporting period. Giving a total length of 2475.4m of tunnel excavated to date. The items carried out during the month can be quantified as follows:

Bridge No. 1

75m of girder cast

Major Events and Issues

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination