![]() |
|||||||||||||||||||||||
Welcome to Our Site! |
|||||||||||||||||||||||
Progress Report > Package IB - South Tunnel Section
During the reporting period 96.1m of Evacuation Tunnel and 136.1m of Main Tunnel Top Heading was excavated, giving a total length of 2475.4m of Evacuation Tunnel and 2532.8m of Main Tunnel Top Heading excavated to date. Bench excavation continued with 136.1m being excavated on the West Side and 256.4m excavated on the East Side. Tunnel lining continued with 42.3m of main tunnel, 43.4m of layby and 69.5m of Electrostatic Precipitator completed. Work continued on the Evacuation Tunnel cut and cover section. Overall a good months progress, slightly up in the main tunnel excavation, but down around 20% in the Evacuation Tunnel. Package IB has now passed the PKIA/IB boundary and Dong Ah – Song Da JV continue to excavate as a subcontractor for Package IA. Main Tunnel A total of 136.1m of Main Tunnel Top Heading was excavated over the reporting period, giving a total length of 2532.8m of Main Tunnel Top Heading excavated to date. Face No.7
Bench excavation
The large geological overbreak between St. 2+119.5 and St. 2+124.5 was backfilled with concrete. Tunnel Lining Concrete for Foundation Beam –289.1m Fr. St. 1+778.9 to St. 2+068 (West Side) Concrete for Foundation Beam –141.2m Fr. St. 1+ 848.2 to St. 1+989.4 (East Side) Concrete for Tunnel Lining – 42.3m (1 block) from St. 6+232.5 to St. 6+190.2 Concrete Lining of layby 43.4m (8 blocks) Concrete lining for EP 69.5m (13 blocks) Backfill grouting of tunnel lining from block 65-122 Cement quantity 8880 kg Installation of mole drain 94m Installation of waterproof membrane 136m Placement of concrete for walkways 660m (East side) 100m (West side) Evacuation Tunnel A total of 96.1m of Evacuation Tunnel was excavated from St. 2+379.3 to Sta. 2+475.4 over the reporting period. Giving a total length of 2475.4m of tunnel excavated to date. The items carried out during the month can be quantified as follows: Bridge No. 1 75m of girder cast Major Events and Issues This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||||||||||