As of June 30, 2003

Physical Progress

Contractor

JV of Dong Ah and Song Da

Commencement of the Works

1st October 2000

Contract Period

1460 days (Until September 30, 2004)

Time Elapsed (days)

996 of 1460 (68.22%) Remaining 464days

Progress

 

Main Tunnel(2417m)

137.4m in this month; 2396.7 in total (100%)

Evacuation Tunnel(2429m)

79.4m in this month; 2379.3m in total (98.68%)

Access Road to Water Reservoir.

Completed 98%

Bridge No.1(58m)

25m of girder casted

Others

 

 

Photographs

South Portal Area - June 2003
Installation of formwork for pedestrian walkway of eastern side
Cleaning drainage ditch
Construction of foundation beam
Inspection of double welding connection
Placement of concrete lining for layby
Pull-out rockbolt
Support for Main tunnel from Km 2+121 to Km 2+124
Setting out and surveying face No. 7
Placement of concrete ling for Electristatic Precipitator
Construction of evacuation tunnel's cut and cover section
Charging for blaasting of evacuation tunnel
Installation of reinforced steel for casting girder
Concrete sample of bridge's girder

Mr. Tri of inspection committee of Communist Party visited the site

Top

Construction Supervision

Summary

During the reporting period 79.4m of Evacuation Tunnel and 137.4m of Main Tunnel Top Heading was excavated, giving a total length of 2379.3m of Evacuation Tunnel and 2396.7m of Main Tunnel Top Heading excavated to date.

Bench excavation continued with 178m being excavated on the West Side and 129.4m excavated on the East Side.

Tunnel lining continued with 10m of main tunnel, 54.9m of layby and 26m of Electrostatic Precipitator completed.

Work commenced on the Evacuation Tunnel cut and cover section.

Overall a poor months progress, slightly down in the main tunnel excavation, but down around 30% in the Evacuation Tunnel.

The Main Tunnel is just over 1m from the PKIA/IB contract boundary.  To reduce PKIA delay a subcontract agreement was signed on June 28 2003 for PKIB to excavate and primary support 450m of PKIA tunnel.

The Main Tunnel is on schedule and the Evacuation Tunnel 5 weeks behind.

Main Tunnel

A total of 137.4m of Main Tunnel Top Heading was excavated over the reporting period, giving a total length of 2396.7m of Main Tunnel Top Heading excavated to date.

Face No.7:  

– 137.4m of Top Heading excavated from St. 2+259.3 to St. 2+396.7

Bench excavation

– 146m of bench excavated from St. 1+834 to St. 1+980 and 32m from St. 2+012 to St. 1+980 (West side).

– 112.1m of bench excavated from St. 1+793.5 to St. 1+905.6 and 17.3m from St. 1+990 to St. 2+007.3 (East side)

The large geological overbreak between St. 2+119.5 and St. 2+124.5 was backfilled with concrete.

Electrostatic Precipitator 

- Excavated 71.5m of bench from St. 0+076.25 to St. 0+147.78

Tunnel Lining

Concrete for Foundation Beam –99.5m Fr. St. 1+679.4 to St. 1+778.9   (West Side)

Concrete for Foundation Beam –129.9m Fr. St. 1+ 718.6 to St. 1+848.2 (East Side)

Concrete for Tunnel Lining – 10m (1 block) from St. 6+257.555 to St. 6+267.555

Concrete Lining of layby 54.9m (9 blocks)

Concrete lining for EP 26m

Backfill grouting of tunnel lining from block 36-65

Concrete for east side duct bank – 540m

Evacuation Tunnel

A total of 79.4m of Evacuation Tunnel was excavated from St. 2+299.9 to St. 2+379.3 over the reporting period. Giving a total length of 2379.3m of tunnel excavated to date.

Bridge No. 1

25m of girder cast

Access Road to Water Reservoir

 

Major Events and Issues

- Mr. Tri, Head of Inspection Committee of Communist Party visited the site.

- Sub-contract agreement for excavation and primary support of 450m for PKIA was signed on June 28, 2003

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination