As of May 31, 2003

Physical Progress

Contractor

JV of Dong Ah and Song Da

Commencement of the Works

1st October 2000

Contract Period

1460 days (Until September 30, 2004)

Time Elapsed (days)

966 of 1460 (66.16%) Remaining 494 days

Progress

 

Main Tunnel(2417m)

138.05m in this month; 2259.3 in total (94.96%)

Evacuation Tunnel(2429m)

134.4m in this month; 2299.9m in total (95.39%)

Access Road to Water Reservoir.

Completed 98%

Bridge No.1(58m)

Complete the construction for concrete work of bridge pier and Northern and Southern abutment.

Others

 

 

Photographs

South Portal Area May 2003
Placement of Concrete for East Cable Curb
Inspection of Double Welding Connection
Placement of Concrete Foundation Beam
Placement of Concrete Lining
Construction of Bench
Main Tunnel Support At Station 2+124.65
Construction of Face No.7
Construction of Evacuation Tunnel
Installation of Formwork for Cross Passage
Placement of Concrete Foundation Beam for EP
Installation of Formwork for Concrete Lining of Electrostatic Precipitator
Drilling Cores for Checking Thickness of Support Shotcrete
SITOC Visited the Site

Top

Construction Supervision

Summary

During the reporting period 134.4m of Evacuation Tunnel and 138.05m of Main Tunnel Top Heading was excavated, giving a total length of 2299.9m of Evacuation Tunnel and 2259.3m of Main Tunnel Top Heading excavated to date.

Bench excavation continued with 120.5m being excavated on the West Side and 156.62m excavated on the East Side.

Tunnel lining continued with 191m of main tunnel completed and 43.77m of layby completed.

Excavation of the Electrostatic Precipitator bench continued, and 71.5m completed.

Overall a disappointing months progress due to poor geological conditions at the start of the month and then the contractor’s implementation of a new survey and drilling method which has slowed progress and increased cycle times from 17-24 hrs in the Main Tunnel.  The Main Tunnel is now 1 week behind schedule and Evacuation Tunnel 5 weeks.

Main Tunnel

A total of 138.05m of Main Tunnel Top Heading was excavated over the reporting period, giving a total length of 2259.3m of Main Tunnel Top Heading excavated to date.

Face No.7:  

- 138.05m of Top Heading excavated from St. 2+121.25 to St. 2+259.3

Bench excavation

– 120.5m of bench excavated from St. 1+713.5 to St. 1+834 (West side).

– 156.62m of bench excavated from St. 1+636.9 to St. 1+793.52 (East side)

Electrostatic Precipitator 

- Excavated 71.5m of bench from St. 0+076.25 to St. 0+147.78

Tunnel Lining

Concrete for Foundation Beam -126.02m Fr. St.1+ 553.43 to St.1+679.43 (West Side)

Concrete for Foundation Beam -161.2m Fr. St.1+ 557.1 to St. 1+718.55 (East Side)

Concrete for Tunnel Lining – 191m (16 blocks) from St. 6+466.591 to St. 6+257.555

Concrete Lining of layby 43.77m (7 blocks)

Backfill grouting of tunnel lining from block 14-36

Installation of mole drainpipe:                                            151 m             

Installation of waterproofing membrane:                             118 m

Evacuation Tunnel

A total of 134.4m of Evacuation Tunnel was excavated from St.2+165.5 to St. 2+299.9 over the reporting period. Giving a total length of 2299.9m of tunnel excavated to date. The items carried out during the month can be quantified as follows:

Explosive: 8930 kg 

Shotcrete 50mm thickness: 1391.7 m2 

SN rockbolts 3m: 6 No.

Access Road to Water Reservoir

Construction of drainage ditch – 158 m

Major Events and Issues

- May 14, 2003, VTV visited the site.

- May 31, 2003, SITOC visited the site.

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination