Progress Report > Package IB - South Tunnel Section
During the reporting period 134.4m of Evacuation Tunnel and 138.05m of Main Tunnel Top Heading was excavated, giving a total length of 2299.9m of Evacuation Tunnel and 2259.3m of Main Tunnel Top Heading excavated to date. Bench excavation continued with 120.5m being excavated on the West Side and 156.62m excavated on the East Side. Tunnel lining continued with 191m of main tunnel completed and 43.77m of layby completed. Excavation of the Electrostatic Precipitator bench continued, and 71.5m completed. Overall a disappointing months progress due to poor geological conditions at the start of the month and then the contractor’s implementation of a new survey and drilling method which has slowed progress and increased cycle times from 17-24 hrs in the Main Tunnel. The Main Tunnel is now 1 week behind schedule and Evacuation Tunnel 5 weeks. Main Tunnel A total of 138.05m of Main Tunnel Top Heading was excavated over the reporting period, giving a total length of 2259.3m of Main Tunnel Top Heading excavated to date. Face No.7:
Bench excavation
Electrostatic Precipitator
Tunnel Lining
Evacuation Tunnel A total of 134.4m of Evacuation Tunnel was excavated from St.2+165.5 to St. 2+299.9 over the reporting period. Giving a total length of 2299.9m of tunnel excavated to date. The items carried out during the month can be quantified as follows:
Access Road to Water Reservoir
Major Events and Issues - May 14, 2003, VTV visited the site. - May 31, 2003, SITOC visited the site.This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||||||||||