As of May 31, 2003

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Commencement of the Works

21 December 2001

Contract period

540 days (Until June 20, 2003)

Time Elapsed (days)

488 of 540 (90.37%) Remaining 52 days

Progress

 

110/22 kV Substation

- Finish the 110kV substation and OCC building.

- Install the Power Transformers, Diesel generators, auxiliary transformer in the sub-station. Deliverd to site 110kV GIS, MV switchboard, UPS, battery, cable, wiring device, luminaires.

110 kV Transmission Line

- 10/14 Tower Foundation competed.

- Manufacturer the steel Towers.

 

Photographs

110/22kV Substation Operation and Control Center Building
Air conditioning duct installation
Main power transformers installed in bays at 110kV substation
Unloading emergency diesel generator
110kV cable duct excavation near operation and control center
110kV overhead transmission line tower assemblies

Top

Construction Supervision

Brick work 100% completed

Redering work inside the building completed 100% and outside the building 30%.

Plastering inside the building complete 85%.

Floor tiles complete 70%

Door frames installation completed.

Canopies above the doors completed.

Duct work for ventilation system completed 80%.

Main transformer installation completed.

Shipment No.5 delivered on site.

Interior lighting and wiring device delivered on site

Excavation for cable duct and manholes started.

110kV Transmission Line Tower foundation completed 70%

manufacturing of switchyard equipment for Lien Chieu substation completed.

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination