Construction Supervision Brick work 100% completed Redering work inside the building completed 100% and outside the building 30%. Plastering inside the building complete 85%. Floor tiles complete 70% Door frames installation completed. Canopies above the doors completed. Duct work for ventilation system completed 80%. Main transformer installation completed. Shipment No.5 delivered on site. Interior lighting and wiring device delivered on site Excavation for cable duct and manholes started. 110kV Transmission Line Tower foundation completed 70% manufacturing of switchyard equipment for Lien Chieu substation completed.This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||||