Contractor
|
JV
of ABB, Kinden and Vinaincon
|
Commencement
of the Works
|
21
December 2001
|
Contract
period |
540
days (Until June 20, 2003) |
Time
Elapsed (days)
|
518
of 540 (95.92%) Remaining 22 days
|
Progress
|
|
110/22
kV Substation |
-
Continue the civil work & finishing work for OCC
Building.
-
Complete 100% of Duct work for Ventilation System.
|
110
kV Transmission Line |
Complete
85% of 110kV Transmission Line Tower Foundation and
start erection of towers.
|
Photographs
 |
110/22kV
Substation operation and control center building
|
 |
Cable
ladder in the cable trench of 110/22kV Substation
OCC building
|
 |
Oil
fitering for 110/22kV transformer
|
 |
Ducting
and exhaust piping for Diesel generator
|
 |
110kV
overhead transmission line tower erection
|
 |
110kV
underground transmission line cable duct
|
During
the reporting month, the Contractor continued the finishing work inside
the building and proceeded the equipment installation. Outside the
building rendering work completed.
On
June 10, 2003, shipment No.6 arrived to site. The Contractor continued
the finishing work in the substation building, installation of diesel
generators, battery and uninteruptable power supply.
The
foundation work for the 110kV Transmission Line tower continued.
Foundations for twelve towers completed. The fabrication of the towers
completed and the tower erection started.
Most
of the switchyard equipment for Lien Chieu substation was shipped. The
mechanical design for Lien Chieu Substation Modification was submitted
for EVNs approval.
Rendering
outside & plastering inside of the building 100 % completed.
Painting
inside the building 50 % completed.
Floor
tiles 95 % completed.
Door
installation 85% completed.
Cable
ladders 95% completed.
Canopies
on the roof completed.
Duct
Work for Ventilation System 100 % completed.
Diesel
Generators 90% completed.
Shipment
no. 6 delivered on site.
Interior
Lighting installation 40% completed.
Excavation
for cable duct and manholes 95% completed.
110kV
Transmission Line Tower Foundations 85% completed.
Erection
of 110 kV Transmission Line Towers started.
|