As of June 30, 2003

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Commencement of the Works

21 December 2001

Contract period

540 days (Until June 20, 2003)

Time Elapsed (days)

518 of 540 (95.92%) Remaining 22 days

Progress

 

110/22 kV Substation

- Continue the civil work & finishing work for OCC Building.

- Complete 100% of Duct work for Ventilation System.

110 kV Transmission Line

Complete 85% of 110kV Transmission Line Tower Foundation and start erection of towers.

Photographs

110/22kV Substation operation and control center building
Cable ladder in the cable trench of 110/22kV Substation OCC building
Oil fitering for 110/22kV transformer
Ducting and exhaust piping for Diesel generator
110kV overhead transmission line tower erection
110kV underground transmission line cable duct

Top

Construction Supervision

During the reporting month, the Contractor continued the finishing work inside the building and proceeded the equipment installation. Outside the building rendering work completed.

On June 10, 2003, shipment No.6 arrived to site. The Contractor continued the finishing work in the substation building, installation of diesel generators, battery and uninteruptable power supply.

The foundation work for the 110kV Transmission Line tower continued. Foundations for twelve towers completed. The fabrication of the towers completed and the tower erection started.

Most of the switchyard equipment for Lien Chieu substation was shipped. The mechanical design for Lien Chieu Substation Modification was submitted for EVNs approval.

Rendering outside & plastering inside of the building 100 % completed.

Painting inside the building 50 % completed.

Floor tiles 95 % completed.

Door installation 85% completed.

Cable ladders 95% completed.

Canopies on the roof completed.

Duct Work for Ventilation System 100 % completed.

Diesel Generators 90% completed.

Shipment no. 6 delivered on site.

Interior Lighting installation 40% completed.

Excavation for cable duct and manholes 95% completed.

110kV Transmission Line Tower Foundations 85% completed.

Erection of 110 kV Transmission Line Towers started.

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination