Welcome to Our Site!
 

 

As of April 30, 2003

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Commencement of the Works

21 December 2001

Contract period

540 days (Until June 20, 2003)

Time Elapsed (days)

458 of 540 (84.81%) Remaining 82 days

Progress

 

110/22 kV Substation

- Complete the civil work of S/S building.

- Delivery of main equipment for S/S.

110 kV Transmission Line

- Foundation excavation for 110kV Transmission Line Tower competed 90%.

Photographs

110/22kV Substation operation and control center building
Painting work for 110kV Substation operation and control room
110kV Overhead transmission line tower foundation re-bar and base concrete
110kV cable unloading on site
2-ton crane capacity test inspected by Engineer

Top

Construction Supervision

In the substation building the priority is on the activities that have to be completed before the installation of the electrical equipment can commence. Although the focus has been on the rooms that will accommodate electrical equipment, there has also been progress in other areas. During the last month the brick work in the building has been practically completed. Most of the walls inside the building have been rendered and plastered. All electrical conduits have been installed. The concrete floor in all rooms have been completed as well as the concrete work for the stairs on the east side and from second floor to roof. Further the roof slab on level 11.6 m has been poured and the canopies above main transformer doors have been made.

Regarding building facility, 2-ton crane installation was completed and got the certificate of government. And manufacturer training will be held when the operator was charged. The ducting work of Air-conditioning and Ventilation System has been commenced and equipments were ordered. 110kV Cable and 24kV Cable have been on site and inspected by Electrical Engineer.

The foundation work for the 110 kV Transmission Line towers have continued. The foundations for five towers have been completed. The fabrication of the towers has started.

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination