As of March 31, 2003

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Commencement of the Works

21 December 2001

Contract period

540 days (Until June 20, 2003)

Time Elapsed (days)

398 of 540 (73.7%) Remaining 142 days

Progress

 

110/22 kV Substation

- Brick work was 98% and rendering 75% completed.

- 22kV GIS and Power Transformer delivered on site.

110 kV Transmission Line

- Foundation excavation for 110kV Transmission Line Tower competed 90%.

 

Photographs

110/22kV Substation Operation and Control Center Building

Plastering Work for 110kV Substation operation and Control Room

10MVA 110/22kV Power Transformer Unloading on Site

110kV Overhead Transmission Line Tower Foundation Lean Concrete

Top

Construction Supervision

The 22 kV indoor switchgear (shipment no.3) arrived to site 19th of March 2003. The power transformers (shipment no. 4) arrived to site 27th of March 2003. Both power transformers were offloaded directly on their foundations inside the substation buildings. No transport damages were noted on these two shipments.

In the substation building the focus has been on the activities that are on the critical path for package V. The work during the month has mainly been brick work, installation of electrical conduits, rendering and plastering. Further the two ton crane in the 110 kV GIS room has been installed and tested and the stairs from first floor to second floor have been made. The work on the canopies above the doors to the GIS rooms has also started. 

The excavation work for the 110 kV Transmission Line has continued and 90% is completed. Further the lean concrete and reinforcement steel work has started. The work on towers no. 6 and no. 11 has been stopped by the land owners claiming that the land acquisition has not been solved. This situation is serious and need to be solved on an urgent basis.

The Mechanical Design of Lien Chieu Substation modification for Variation Order No.1 has been proceeding during this month. These drawings will be submitted for approval in April 2003.

Brick work was 98% completed.

Rendering inside the building 75% completed.

2 ton crane installed and tested.

22kV GIS were delivered on site.

Power transformer were delivered on site

110kV Transmission Line Tower Foundation Excavation was 90% completed.

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination