Welcome to Our Site!
 

 

As of February 28, 2003

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Commencement of the Works

21 December 2001

Time Elapsed (days) 398 of 540 (73.7%) Remaining 142 days

Progress

 
110/22 kV Substation

- Brick work was 90% completed.

- 110 GIS was delivered on site.

110 kV Transmission Line

- 110kV Transmission Line Tower foundation excavation started.

 

Photographs

110/22kV Substation Operation and Control Center Building
Earthing Register Measurement for Access
110kV GIS Delivery on Site
110kV Overhead Transmission Line Tower Foundation Excavation

 

Top

Construction Supervision

The focus of work activity during the month delivered 110kV GIS on site. The customs procedure was completed smoothly. The manufacturing and shipment of the other equipment and materials also held on after another.

The brick work was completed 90% so that the main substation equipment installation proceeds without delay. In addition, the preparation for plastering and painting work was held to complete before main substation equipment installation.

After Lunar New Year Holidays, the 110kV Overhead Transmission Line Work was commenced. And until the end of the month, 60% of the whole of excavation work was completed and the Excavation for 2 towers was completed. The re-bar testing was holed for concreting work and the result was good.

The measuring of earth resistance was held to confirm the design for earthing protection system.

The detail design of Lien Chieu Substation modification for Variation Order No.1 was submitted.

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination