The focus of work activity during the mnth concentrate on fabrication of R/F Steel and formwork to the roof slab. The 150 cubic meters concrete pour took place on Wednesday 22nd January, thus “topping” out the substation and effectively completing the frame structure of the building. Other concreting work included beams, columns and welded through progress of the columns and roof slab construction as appropriate. The Monthly Safety Audit took place as scheduled. The second and final factory inspetion visit took place from January 8 to January 17, 2003.This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||