As of January 31, 2003

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Commencement of the Works

21 December 2001

Time Elapsed (days) 370 of 540 (68.52%) Remaining 170 days

Progress

 
110/22 kV Substation

- Fabrication of R/F steel and formwork for the roof slab.- Shipment of power transformer and 110kV GIS carried out.

110 kV Transmission Line

- Complete Factory Acceptance for Power Distribution Monitoring & Control System.

 

Photographs

Rebar Roof Slab of NW Corner 110/22kV S/S OCC Building
Preparing Concrete Pour of Roof 110/22kV S/S OCC Building
Pouring Concrete Slab of 110kV/22kV S/S OCC Building
Concrete work for roof slab of 110/22kV S/S OCC Building
Concrete work for roof slab of 110/22kV S/S OCC Building

Top

Construction Supervision

The focus of work activity during the mnth concentrate on fabrication of R/F Steel and formwork to the roof slab.

The 150 cubic meters concrete pour took place on Wednesday 22nd January, thus “topping” out the substation and effectively completing the frame structure of the building.

Other concreting work included beams, columns and welded through progress of the columns and roof slab construction as appropriate.

The Monthly Safety Audit took place as scheduled.

The second and final factory inspetion visit took place from January 8 to January 17, 2003.

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination