Welcome to Our Site!
 

 

As of December 31, 2002

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Commencement of the Works

21 December 2001

Time Elapsed (days) 340 of 540 (62.96%) Remaining 200 days

Progress

 
110/22 kV Substation

- Concrete work for second floor of OCC completed.

- Shipment of power transformer and 110kV GIS carried out.

110 kV Transmission Line

- Access to site granted to Contractor.

- Connection to national power network is under design.

 

Photographs

Concrete Pour 2nd Floor Slab of NE corner 110/22kV S/S OCC Building
Concrete Pour 2nd Floor Slab of East Wall 110/22kV S/S OCC Building
Re-bar & grounding for the 2nd Floor Slab of 110/22kV S/S OCC Building
Formwork for Roof Slab & Beam of 110/22kV S/S OCC Building

Top

Construction Supervision

Construction of 110kV substation and operation control center building reached to 64%.

Detailed design and engineering and equipment of electrical system reached to 74%.

Preocurement of materials and equipment reached to 33%.]

The nominated company for equipment importing was approved by Ministry of Tranportation and Ministry of Trade.

Power transformer and 110kV GIS was planned for shipment.

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination