Construction Supervision Construction of 110kV substation and operation control center building reached to 64%. Detailed design and engineering and equipment of electrical system reached to 74%. Preocurement of materials and equipment reached to 33%.] The nominated company for equipment importing was approved by Ministry of Tranportation and Ministry of Trade. Power
transformer and 110kV GIS was planned for shipment. This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||