As of November 30, 2002

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Commencement of the Works

21 December 2001

Time Elapsed (days) 310 of 540 (57.41%)

Progress

 
110/22 kV Substation

Civil work of substation building under contruction

Prepare delivery of power transformer and GIS.

Other equipment is under manufacture.

110 kV Transmission Line

Construction of tower foundation is waiting for access to site.

Variation for connection point approved by MOT.

 

Photographs

Corrosion-proofing for the Transformer Oil Drain Pipe of Main Transformer
Column from 1st floor to 2nd floor of 110/22kV S/S OCC Bulding
Form work for the 2nd fllor slab of 110/22kV S/S OCC Building
Re-bar work for 2nd floor beam of 110/22kV S/S OCC Building

Top

Construction Supervision

The Project Package V has progressed satisfactorily during the month of November. The main construction work of the Package has been the Operation Control Center Building. In particularly, the erection of the brick walls to second floor slab level and the construction of the formwork for the floor slab. The cable trench works have been concreted and some final dressing has been carried out. And the earthing network extended to second floor level. External ground works for the drainage andn oil collection tank are in progress. Approval of Contractor drawings continues but there are still outstanding issues.

The outstanding item of approval of the variation order for Lien Chieu Substation remains and will impact on the completion date of Package V. The commencement of the work on the 110kv transmission line is delayed. The required documentation is still not availlable at the end of November 2002.

Activities for Coming Months

Permanent Works

Pouring Concrete for Cable Trenches, Columns, First Floor Beams and First Floor Slab will be completed after completion of Backfilling up to First Floor of Substation and Reinforcing Steel installation. And regarding Earthing System, First Floor Slab Grid installation will be completed and in columns from First Floor to Second Floor will be continued.

Main Substation Equipments are under manufacturing and Manufacturing of some items will be started after getting Engineer’s Approval. Mechanical and Electrical Equipments for 110/22kV Substation Operation and Control Center Building will be started to order after Engineer’s Approval.

Regarding 110kV Overhead Transmission Line, we are waiting for issue Engineer’s Access to Site. Cutting Tree and Foundation Work will be started as soon as we will get Engineer’s Access to Site and Employer will settle Land Acquisition, Cutting Tree Compensation and Mine Removal Certificate.

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination