Welcome to Our Site!
 

 

As of October 30, 2002

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Commencement of the Works

21 December 2001

Time Elapsed (days) 280 of 540 (51.85%)

Progress

 
110/22 kV Substation 80% construction of foundation completed. Concrete work of some columns to first floor.
110 kV Transmission Line 0% construction design completed, awaiting site access. Connection approval (V.O.1) awaited.

 

Photographs

Unit Masonry and Structural Backfilling Work for 110/22kV S/S OCC Building
Formwork for Columns of 110/22kV S/S OCC Building
Measurement of Earthing Resistance of Underground Mesh
Installation of Earthing Wire from Ground Earthing Mesh to Second Floor
PVC Pipe Instalation for Drain System

Top

Construction Supervision

The Project Package V has progressed satisfactorily during the month of October. The main work of the package has been the continuation of the construction of the Operation Control Center Building in particular the construction of main columns to second floor level, the main cable trenches for the equipment rooms and the progressive installation of the building earthing system. Approval of Contractor drawings continues but there are still outstanding issues.

The need of all equipment within the building are almost fully defined and the location of most auxiliary items specified.

Equipment approval and procurement is continuing. However the outstanding item of approval of the variation order for Lien Chieu Substation may impact on the completion date of Package V. The commencement of the work on the 110kv transmission line is imminent but is awaiting the issuance of the land acquisition, compensation for plants and the mine clarance certification. This documentation is expected to be completed during November 2002

Activities for Coming Months

Permanent Works

Pouring Concrete for Cable Trenches, Columns, First Floor Beams and First Floor Slab will be completed after completion of Backfilling up to First Floor of Substation and Reinforcing Steel installation. And regarding Earthing System, First Floor Slab Grid installation will be completed and in columns from First Floor to Second Floor will be continued.

Main Substation Equipments are under manufacturing and Manufacturing of some items will be started after getting Engineer's Approval. Mechanical and Electrical Equipments for 110/22kV Substation Operation and Control Center Building will be started to order after Engineer's Approval.

Regarding 110kV Overhead Transmission Line, we are waiting for issue Engineer's Access to Site. Cutting Tree and Foundation Work will be started as soon as we will get Engineer's Access to Site and Employer will settle Land Acquisition, Cutting Tree Compensation and Mine Removal Certificate.

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination