As of April 30, 2003

Physical Progress

Contractor

JV of Thang Long and Truong Son

Commencement of the Works

1st July 2001

Contract period

900 days (Until December 31, 2003)

Time Elapsed (days)

663 of 900 (73.67%) Remaining 237 days

Progress

 

North Approach

Complete 100%

Lang Co Bridge (867m)

Total 199 nos of bored piling completed up to present. Remaining 19nos. Completion 91%

South Approach

Embankment finished up to 1000m3

Photographs

General Sight View of Lang Co Bridge

Construction A1 Abutment: Bored Pile

General Sight View of Bored Pile of P1, A1 Abutment

Construction of Bored Pile P1 Pier (D=1600mm)

Construction of P16 Pier: Stage 1

Construction of P16 Pier Stem: Stage 1

Construction of P16 Pier Stem: Base, Stage 1

Construction of Pier 16 Pier

Completed P20 Pier

Construction Superstructure of Span P26, P25, P24

Top

Construction Supervision

Project schedule has already past 22 months and remaining 08 months now.  Percent completion is ~ 62% based on the activity completion (Including: ~ 46% of Bridge work and ~ 16% of Road and general requirement work). 

Bored Piling

Total 218 nos. of bored piles with different diameter are required for foundation.

199 nos. of bored piles has completed and remaining 19 nos. Percent completion of bored piling is 91%.  Foundation of Piers: P1, P3 and North Abutment A1 is under construction of piling work and 2 foundations such as, P2, P4 remaining piling work.

Substructure

2 abutments and 25 piers are required for Lang Co Bridge.

15 piers and 1 abutment have completed up to cross head such as P7, P8, P9, P9, P11, P14, P17, P18, P19, P20, P21, P22, P23, P24, P25 and South Abutment.

4 piers are under construction of structure work such as P6, P13, P15, P16. Including P16 is finished pier Base. Sheet piles for pit excavation of P6, P13 and P15 are driving now. P1, P2, P3, P4, P5, P12 and A1 are not active not completely.

Superstructure

Preparation of launching at south abutment has just commenced on 10 February 2003.

Launching of Span26, 25, 24, 23 and 22 are completed. Concrete of Diaphragm of span 26, 25 and 24 are completed too. Reinforcing for Deck slab of span 26, 25 and 24 are preparing now.

Approach Road

North approach road has completed for surcharge fill and South approach road is finished embankment.

Girder Production

Total 130 nos. of PCI girders are required production.

2 places of girder production yard are under operation and 60 nos. of PCI girders has completed production.  Percent completion of girder production is 46%.

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination