As of March 31, 2003

Physical Progress

Contractor

JV of Thang Long and Truong Son

Commencement of the Works

1st July 2001

Contract period

900 days (Until December 31, 2003)

Time Elapsed (days)

633 of 900 (70.33%) Remaining 267 days

Progress

 

North Approach

Road and Surcharge fill completed 100%

Lang Co Bridge (867m)

Total 189 nos of bored piling completed up to present. Remaining 29nos. Completion 86%

South Approach

Embankment finished

Photographs

General Sight View of Lang Co Bridge

Construction of Bored Pile P6 Pier (D = 1600mm)

Construction Bored Pile of P6 Pier (Pile No.2)

Construction P10 Pier System: stage 1, Stage 2, Stage 3

Construction P11 Pier : Stage 1,, Stage 2

Excavation of P16 Pier Foundation Pit

Construction P19: Cross Head

Construction P20 Pier: Base

Installation of Floating System

Launching Girder Span No.22

General Sight View of Launching Girder

Casing D = 1600mm

Top

Construction Supervision

Bored Piling

Total 218 nos. of bored piles with different diameter are required for foundation.

189 nos. of bored piles has completed and remaining 29 nos. Percent completion of bored piling is 86%.  1 foundation P6 is under construction of piling work and 5 foundations such as North Abutment, P1, P2, P3, P4, and P5 remaining piling work.

Substructure

2 abutments and 25 piers are required for Lang Co Bridge.

11 piers and 1 abutment have completed up to cross head such as P7, P8, P9, P14, P17, P18, P21, P22, P23, P24, P25 and South Abutment.

7 piers are under construction of structure work such as P10, P11, P12, P13, P15, P16 and P19. Including P19 is finishing now; P11, P12 and P15 are not active not completely.

Superstructure

Preparation of launching at south abutment has just commenced on 10 February 2003.

Launching of Span26, 25 and 24 has commenced on 24 March.2003 and it is finished. Span 23 is continued.

Approach Road

North approach road has completed for surcharge fill and South approach road is finished embankment.

Girder Production

Total 130 nos. of PCI girders are required production.

2 places of girder production yard are under operation and 56 nos. of PCI girders has completed production.  Percent completion of girder production is 43%.

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination