Progress Report > Package IIA - Lang Co Bridge Section
Photographs Bored Piling Total 218 nos. of bored piles with different diameter are required for foundation. 189 nos. of bored piles has completed and remaining 29 nos. Percent completion of bored piling is 86%. 1 foundation P6 is under construction of piling work and 5 foundations such as North Abutment, P1, P2, P3, P4, and P5 remaining piling work. Substructure 2 abutments and 25 piers are required for Lang Co Bridge. 11 piers and 1 abutment have completed up to cross head such as P7, P8, P9, P14, P17, P18, P21, P22, P23, P24, P25 and South Abutment. 7 piers are under construction of structure work such as P10, P11, P12, P13, P15, P16 and P19. Including P19 is finishing now; P11, P12 and P15 are not active not completely. Superstructure Preparation of launching at south abutment has just commenced on 10 February 2003. Launching of Span26, 25 and 24 has commenced on 24 March.2003 and it is finished. Span 23 is continued. Approach Road North approach road has completed for surcharge fill and South approach road is finished embankment. Girder Production Total 130 nos. of PCI girders are required production. 2 places of girder production yard are under operation and 56 nos. of PCI girders has completed production. Percent completion of girder production is 43%. This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team |
|
||||||||||||||||||