Progress Report > Package IIA - Lang Co Bridge Section
Photographs Project Schedule passed 23 months and 07 months remained from the reporting month. Completion percentage was 67% based on the activities completion (including 50% of bridge work and 17% of road and general requirement work). Bored Piling Total 218 nos of bored piles with different diameter are required for foundation. 209 nos. of bored piles completed and 09 nos. remained. Completion percentage of bored piling is 96%. Foundation of piers: P3 was under construction of piling work and 2 foundations of P2, P4 remained the piling work. Substructure 2 abutments and 25 piers are required for Lang Co Bridge. 1 5 piers and 1 abutment completed up to cross head such as P7, P8, P9, P11, P14, P16, P17, P18, P19, P20, P21, P22, P23, P24, P25 and South Abutment. 5 piers and abutment are under construction of structure work such as P6, P12, P13, P15 and A1. Sheet piles for pit excavation of P12 was under driving. P1, P2, P3, P4, P5 were under construction. Superstructure Preparation of lauching at south abutment started on Feb 2003. Launching of span 26, 25, 24, 23, 22, 21 and 19 completed. Concrete of diaphragm of span 26, 25, and 24 completed too. Reinforcing for Deck Slab of span 26, 25, 24 completed and concrete cast for those spans were carried out but not completed. Approach Road North approach road completed for surcharge fill and south approach road completed the embankment. Girder Production Total 130 nos. of PCI girders were required to produce. 2 places of girders prodction yard were under operation and 68 nos. of PCI girders completed the production. Completion percentage of girder production was 52%. This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team |
|
||||||||||||||||||