As of May 31, 2003

Physical Progress

Contractor

JV of Thang Long and Truong Son

Commencement of the Works

1st July 2001

Contract period

900 days (Until December 31, 2003)

Time Elapsed (days)

693 of 900 (77%) Remaining 207 days

Progress

 

North Approach

Completion of 100% embankment and 2/3 round culvert. Box culvert, base and asphalt are under construction.

Lang Co Bridge (867m)

Completion of 209/219 bore piles (96%); 17/27 abutment and Pier. Cast 88/130 girder (52%). Launching 35 girder, cast of deck slab 3 spans.

South Approach

Completion of 100% embankment, 1/2 of base layer.

Photographs

General Sight View of Lang Co Bridge
Construction of A1: Foundation
Construction of P3 Pieer: Border Pile (1600mm)
Construction of Bored Pile P3 Pier (D=1600mm)
Construction of P6: Foundation
Construction of P13: Foundation
Construction of P15 Pier: Foundation
Construction of P16 Pier: Stage 1
Construction Superstructure of Span P25, 26
Construction of Footing at Toll Plaza

Top

Construction Supervision

Project Schedule passed 23 months and 07 months remained from the reporting month. Completion percentage was 67% based on the activities completion (including 50% of bridge work and 17% of road and general requirement work). 

Bored Piling

Total 218 nos of bored piles with different diameter are required for foundation.

 209 nos. of bored piles completed and 09 nos. remained. Completion percentage of bored piling is 96%. 

Foundation of piers: P3 was under construction of piling work and 2 foundations of P2, P4 remained the piling work.

Substructure

2 abutments and 25 piers are required for Lang Co Bridge. 1

5 piers and 1 abutment completed up to cross head such as P7, P8, P9, P11, P14, P16, P17, P18, P19, P20, P21, P22, P23, P24, P25 and South Abutment. 5 piers and abutment are under construction of structure work such as P6, P12, P13, P15 and A1. 

Sheet piles for pit excavation of P12 was under driving. P1, P2, P3, P4, P5 were  under construction.

Superstructure

Preparation of lauching at south abutment started on Feb 2003. 

Launching of span 26, 25, 24, 23, 22, 21 and 19 completed. Concrete of diaphragm of span 26, 25, and 24 completed too. 

Reinforcing for Deck Slab of span 26, 25, 24 completed and concrete cast for those spans were carried out but not completed.

Approach Road

North approach road completed for surcharge fill and south approach road completed the embankment.

Girder Production

Total 130 nos. of PCI girders were required to produce. 

2 places of girders prodction yard were under operation and 68 nos. of PCI girders completed the production. Completion percentage of girder production was 52%.

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination