Progress Report > Package IV - Mechanical Works
Summary Study the layout of cable ducts and water pipes in the cable trough in corordination with PK3 Constractor Study the work schedule based on the coordination with other Contractors and considered detailed conditions for access to the site. Prepare the shop drawing of the ventilation equipment for approval Checked the situation of power supply with the Electrical Contractor with reference to soft starting of the jet fan mortors. Study the detailed proposal for change of water catchment source Make the contract signing with the Vietnamese Sub-Contractors Study the proposal for modification of the existing water supply & water treatment system Study the modification of ventilation facilities Start the ground leveling work for site office and warehouse Previous