As of December 31, 2002

Physical Progress

Contractor

Matsushita - Itochu Consortium

Commencement of the Works

13 March 2002

Time Elapsed (days) 288 of 1080 (26.67%) Remaining 792 days

Progress

 
  - Site establishment and mobilization are being prepared.
  - Installation of water pipes under the pump room floor completed.

 

Photographs

Top

Construction Supervision

Carry out the coordination meetings with other Contractors

Carry out the construction work and pressure test for underground piping of the pump room

Study the modification of ventilation facilities

Study the detailed proposal for change of water catchment sauce

Study proposal for modification of the existing water supply & water treatment system

Conclude a contract with Vietnamese subcontractors

Continue to preparing shop drawings for the ventilation equipment

Decide the detailed design of site office and warehouse

Hold a kick-off party jointly hosted by Package 3 and Package 4 on Dec. 7

Top

Previous month / Next month

This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination