![]() |
|||||||||||||||||||||
|
Welcome to Our Site! |
|||||||||||||||||||||
|
Progress Report > Package IB - South Tunnel Section
During the reporting period 92.2m of Evacuation Tunnel and 132.16m of Main Tunnel Top Heading was excavated, giving a total length of 1714.38m of Evacuation Tunnel and 1677.46m of Main Tunnel Top Heading excavated to date. Bench excavation continued with 322.3m being excavated on the West Side and 358.8m excavated on the East Side. Tunnel lining continued with 180m of tunnel completed. Excavation was down over the reporting period due to poor geological conditions in both the Main and Evacuation Tunnel. Over the reporting period there was no recovery against the original clause 14 construction schedule. The Main Tunnel is three weeks behind programme and Evacuation nine weeks. It is expected that progress over the next month will be poor due to the poor geology and the fact that tunnel lining is suspended as there is no lining membrane on site. Evacuation Tunnel A total of 92.2m of Evacuation Tunnel was excavated from St. 1+622.2 to St. 1+714.38 over the reporting period. Giving a total length of 1714.38m of tunnel excavated to date. The items carried out during the month can be quantified as follows: Blasting: 6085 kg Shotcrete 50mm thickness: 1845.1 m2 Wire mesh CQS6: 318.4m2 SW rockbolts 3m long 45 pieces SW rockbolts 4m long 78 pieces Main Tunnel A total of 132.16m of Main Tunnel Top Heading was excavated over the reporting period, giving a total length of 1677.46m of Main Tunnel Top Heading excavated to date. Face No.7 – 132.16m of Top Heading excavated from St. 1+545.3 to St. 1+677.46 Bench excavation – 195.4m of bench excavated from St. 0+774.7 to St. 0+970.1 and 126.9m from St. 1+097 to St. 0+970.1 (West side). – 164.35m of bench excavated from St. 0+764 to St. 0+928.35, 151.95m from St. 1+080.3 to St. 0+928.35, 42.5m from St. 1+097 to St. 1+139.5. The items carried out during the month can be quantified as follows: Face No. 7: Excavation of 132.16m Top Heading Blasting: 18597 kg Wire mesh CQS6: 473m2 Shotcrete 50mm thickness: 2975.72 m2 SN rockbolt 3m: 70 No. SN rockbolts 4m: 186 No. SW rockbolt 3m: 31 No. SW rockbolt 4m: 120 No. Bench Excavation Blasting: 5708 kg Shotcrete for temporary support 50mm: 1381.1m2 SN rockbolt 3m 6 No. Concrete Concrete for Foundation Beam -223m Fr. St. 0+527 to St. 0+750 West Side Concrete for Foundation Beam –203m Fr. St. 0+542 to St. 0+745 East Side Quantity 206.6m3 Concrete for Tunnel Lining - 180m from St. 7+745.825 to St. 7+536.57 Quantity 2461.6m3 Installation of Mole Drain: 345m Installation of Waterproofing Membrane: 130m of Tunnel Access Road to Water Reservoir Completed 50m of drainage ditch Bridge No. 1 Excavation for the South Abutment: 218 m3 Major Events and Issues This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||||||||