As of January 31, 2003

Physical Progress

Contractor

JV of Dong Ah and Song Da

Commencement of the Works

1st October 2000

Time Elapsed (days) 848 of 1460 (58.08%) Remaining 612 days

Progress

Main Tunnel(2417m)

45.04m in this month; 1,722.5m in total(70.91%)

Evacuation Tunnel(2429m)

88.23m in this month; 1,802.6m in total(74.58%)

Access Road to Water Reservoir.

Under construction

Bridge No.1(58m)

Excavation for South Abutment: 85m3

Others

 

Photographs

South Tunnel Portal
Fixing of Waterproofing Membrane
Concreting Revision Pipe
Cleaning for Foundation Beam Concrete
Placement of Conrete for Foundation Beam
Drilling of Bench
Installation of Wire Mesh for Main Tunnel
Installation of Rockbolt for Main Tunnel
Construction of Main Tunnel

Drilling of Face No. 7

Placement of Concrete for Evacuation Tunnel
Placement of Concrete for Evacuation Tunnel
Construction of South Abutment

Top

Construction Supervision

Summary

During the reporting period 92.2m of Evacuation Tunnel and 132.16m of Main Tunnel Top Heading was excavated, giving a total length of 1714.38m of Evacuation Tunnel and 1677.46m of Main Tunnel Top Heading excavated to date.

Bench excavation continued with 322.3m being excavated on the West Side and 358.8m excavated on the East Side.

Tunnel lining continued with 180m of tunnel completed.

Excavation was down over the reporting period due to poor geological conditions in both the Main and Evacuation Tunnel.

Over the reporting period there was no recovery against the original clause 14 construction schedule.  The Main Tunnel is three weeks behind programme and Evacuation nine weeks.

It is expected that progress over the next month will be poor due to the poor geology and the fact that tunnel lining is suspended as there is no lining membrane on site.

Evacuation Tunnel

A total of 92.2m of Evacuation Tunnel was excavated from St. 1+622.2 to St. 1+714.38 over the reporting period. Giving a total length of 1714.38m of tunnel excavated to date. The items carried out during the month can be quantified as follows:

Blasting:                                                          6085 kg

Shotcrete 50mm thickness:                            1845.1 m2

Wire mesh CQS6:                                          318.4m2

SW rockbolts 3m long                                                45 pieces

SW rockbolts 4m long                                                78 pieces

Main Tunnel

A total of 132.16m of Main Tunnel Top Heading was excavated over the reporting period, giving a total length of 1677.46m of Main Tunnel Top Heading excavated to date.

Face No.7 – 132.16m of Top Heading excavated from St. 1+545.3 to St. 1+677.46

Bench excavation  – 195.4m of bench excavated from St. 0+774.7 to St. 0+970.1 and  126.9m from St. 1+097 to St. 0+970.1 (West side).

– 164.35m of bench excavated from St. 0+764 to St. 0+928.35, 151.95m from St. 1+080.3 to St. 0+928.35, 42.5m from St. 1+097 to St. 1+139.5.

The items carried out during the month can be quantified as follows:

Face No. 7: Excavation of 132.16m Top Heading

          Blasting:                                                          18597 kg

          Wire mesh CQS6:                                          473m2            

          Shotcrete 50mm thickness:                           2975.72 m2

          SN rockbolt 3m:                                              70 No.

          SN rockbolts 4m:                                            186 No.

          SW rockbolt 3m:                                             31 No.

          SW rockbolt 4m:                                             120 No.

Bench Excavation

          Blasting:                                                          5708 kg

          Shotcrete for temporary support 50mm:        1381.1m2

          SN rockbolt 3m                                               6 No.

Concrete

          Concrete for Foundation Beam -223m Fr. St. 0+527 to St. 0+750 West Side

          Concrete for Foundation Beam –203m Fr. St. 0+542 to St. 0+745 East Side

          Quantity                                                           206.6m3

          Concrete for Tunnel Lining - 180m from St. 7+745.825 to St. 7+536.57

          Quantity                                                           2461.6m3

          Installation of Mole Drain:                                345m

          Installation of Waterproofing Membrane:        130m of Tunnel

Access Road to Water Reservoir

          Completed 50m of drainage ditch

Bridge No. 1

          Excavation for the South Abutment:                           218 m3

Major Events and Issues

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination