As of February 28, 2003

Physical Progress

Contractor

JV of Dong Ah and Song Da

Commencement of the Works

1st October 2000

Time Elapsed (days) 876 of 1460 (60%) Remaining 584 days

Progress

Main Tunnel(2417m)

86.32m in this month; 1,808.82m in total (76.01%)

Evacuation Tunnel(2429m)

115.5m in this month; 1,918.1m in total (79.55%)

Access Road to Water Reservoir.

Under construction

Bridge No.1(58m)

Excavation for South Abutment

Others

 

Photographs

South Tunnel Portal
Fixing of Waterproofing Membrane
Inspection of Double Welded Connection
Cleaning for Foundation Beam Concrete
Placement of Concrete for Foundation Beam
Shotcrete for Finish
Compacting the Foundation for Fixing Rails for Second Formwork
Placement of Concrete Lining by the Second Formwork
Placement of Concrete Lining by the First Formwork
Construction of Face No.7
Drilling of Evacuation Tunnel
Electrostatic
Mucking of Electrostatic Precipitator

Top

Construction Supervision

Summary

During the reporting period 115.5m of Evacuation Tunnel and 86.32m of Main Tunnel Top Heading was excavated, giving a total length of 1918.1m of Evacuation Tunnel and 1808.82m of Main Tunnel Top Heading excavated to date.

Bench excavation continued with 43.19m being excavated on the West Side and 90.9m excavated on the East Side.

Tunnel lining continued with 199.33m of tunnel completed.

Excavation of the Electrostatic Precipitator continued with 62.36m excavated.

Excavation was down over the reporting period due to poor geological conditions in Main Tunnel, the large amount of plant breakdowns and the Tet holiday.

The Main Tunnel has now passed through the poor ground and is now advancing smoothly.

The second lining form commenced operation.

Over the reporting period time was lost against the original clause 14 construction schedule.  The Main Tunnel is five weeks behind programme and Evacuation 10 weeks.

It is predicted that excavation progress will improve over the next reporting period but tunnel lining will again be down as there is no waterproof membrane on site.

Evacuation Tunnel

A total of 115.5m of Evacuation Tunnel was excavated from St. 1+802.6 to St. 1+918.1 over the reporting period. Giving a total length of 1918.1m of tunnel excavated to date. The items carried out during the month can be quantified as follows:

Explosive:                                          7737 kg

Shotcrete 50mm thickness:                       1265.5 m2

Main Tunnel

A total of 86.32m of Main Tunnel Top Heading was excavated over the reporting period, giving a total length of 1808.82m of Main Tunnel Top Heading excavated to date.

Face No.7:  86.32m of Top Heading excavated from St. 1+722.5 to St. 1+808.82

Bench excavation: 

- 43.19m of bench excavated from St. 1+259 to St. 1+302.19 (West side).

- 90.9m of bench excavated from St. 1+260 to St. 1+350.9 (East side)

Electrostatic Precipitator: Excavated 62.36m of tunnel from Sta. 0+25.34 to Sta. 0+087.7

Tunnel Lining

Concrete for Foundation Beam –293.52m Fr. St. 0+937.5 to St. 1+231.015 (West Side)

Concrete for Foundation Beam –209.79m Fr. St. 0+948.23 to St. 1+158.022 (East Side)

Concrete for Tunnel Lining – 199.331m (17 blocks) from St. 7+396.03 to St. 7+324.21

Installation of waterproofing membrane:                             362m

Access Road to Water Reservoir

          Completed 50m of drainage ditch

Bridge No. 1

          Excavation for the South Abutment:                           218 m3

Major Events and Issues

- The site was closed for Tet Holiday from January 29, 2003 to February 4, 2003.

- On February 3, 2003 General Director of Vietnam Railway Department visited the site.

- On February 22, 2003, VTV1 of Vietnam Television visited and made news features of the site.

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination