![]() |
|||||||||||||||||||||
|
Welcome to Our Site! |
|||||||||||||||||||||
|
Progress Report > Package IB - South Tunnel Section
During the reporting period 114.7m of Evacuation Tunnel and 148.8m of Main Tunnel Top Heading was excavated, giving a total length of 1622.3m of Evacuation Tunnel and 1545.3m of Main Tunnel Top Heading excavated to date. Bench excavation continued with 242.40m being excavated on the West Side and 255.25m excavated on the East Side. Excavation of vehicle cross passage at St. 1+511.005 was completed. Tunnel lining continued with 120m of tunnel completed. Excavation is advancing well and compared to the original schedule shows the Main Tunnel being three weeks behind programme and the Evacuation Tunnel nine weeks. At current rates excavation should be back on programme by early 2003. Tunnel lining continued and the scheduled progress for the month attained. Overall a good months production with all activities hitting there required progress rates.
A total of 114.7m of Evacuation Tunnel was excavated from St. 1+507.5 to St. 1+622.2 over the reporting period. Giving a total length of 1622.2m of tunnel excavated to date. The items carried out during the month can be quantified as follows:
Vehicle Cross passage St. 1+511.005 A total of 114.7m of Evacuation Tunnel was excavated from St. 1+507.5 to St. 1+622.2 over the reporting period. Giving a total length of 1622.2m of tunnel excavated to date. The items carried out during the month can be quantified as follows:
A total of 148.8m of Main Tunnel Top Heading was excavated over the reporting period, giving a total length of 1545.3m of Main Tunnel Top Heading excavated to date.
Completed 80m of drainage ditch and 1 No. Culvert.
Excavation for the South Abutment: 100 m3 Major Events and Issues
Activities for Coming Month
Construction drain: 50m
Placement of concrete for Bridge Abutment: 70m3
Excavation of Evacuation Tunnel: 140m from St. 1+622.2 to St. 1+762.2 Excavation of Face 7 of Main Tunnel : 140m from Km 1+545.3 to Km 1+685.3 Excavation and support of bench:250m from Km 0+725.2 to Km 0+875.2 Concrete placement for Tunnel Foundation: 200m3 Placement of concrete lining: 156m - 13 blocks Installation of waterproofing membrane: 132m Installation of Mole Drain: 100m
Placement of foundation concrete beam, drainpipe and cover of rockbolt heads. This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||||||||