As of November 30th, 2002

Physical Progress

Contractor

JV of Dong Ah and Song Da

Commencement of the Works

1st October 2000

Time Elapsed (days) 788 of 1460 (53.97%)

Progress

Main Tunnel(2417m)

+ 148.8m - 1545.3m (63.93%)

Evacuation Tunnel(2429m)

+ 114.7m - 1622.2m (66.78%)

Access Road to Water Reservoir.

Completed 80m of drainage ditch and 1 No. culvert

Bridge No.1(58m)

Excavation for South Abutment: 100m3

Others

 

Photographs

South tunnel portal
Construction of Face No. 7
Cutting head of rockbolts
Covering head of rocbolts
Shotcreting for finishing surface to installation of water membrane
Installation of waterproofing membrane
Fixing of geotextile for lining of Main Tunnel
Placement of concrete for fire-fighting niche
Placement of concrete for foundation beam
Construction of mole drain pipe
Placement of concrete for lining of Main Tunnel
Construction of bench
Shotcreting for support of bench
Vehicle cross passage No. 9
Mucking of Evacuation Tunnel

 

Top

Construction Supervision

Summary

During the reporting period 114.7m of Evacuation Tunnel and 148.8m of Main Tunnel Top Heading was excavated, giving a total length of 1622.3m of Evacuation Tunnel and 1545.3m of Main Tunnel Top Heading excavated to date.

Bench excavation continued with 242.40m being excavated on the West Side and 255.25m excavated on the East Side.

Excavation of vehicle cross passage at St. 1+511.005 was completed.

Tunnel lining continued with 120m of tunnel completed.

Excavation is advancing well and compared to the original schedule shows the Main Tunnel being three weeks behind programme and the Evacuation Tunnel nine weeks. At current rates excavation should be back on programme by early 2003.

Tunnel lining continued and the scheduled progress for the month attained.

Overall a good months production with all activities hitting there required progress rates.

  • Evacuation Tunnel

A total of 114.7m of Evacuation Tunnel was excavated from St. 1+507.5 to St. 1+622.2 over the reporting period. Giving a total length of 1622.2m of tunnel excavated to date. The items carried out during the month can be quantified as follows:

Blasting:7829 kg

Shotcrete 50mm thickness:  1203.5 m2

Vehicle Cross passage St. 1+511.005

A total of 114.7m of Evacuation Tunnel was excavated from St. 1+507.5 to St. 1+622.2 over the reporting period. Giving a total length of 1622.2m of tunnel excavated to date. The items carried out during the month can be quantified as follows:

Blasting:1800 kg

Shotcrete 50mm thickness:  272 m2

SN rockbolts 4m long: 4 No.

  • Main Tunnel

A total of 148.8m of Main Tunnel Top Heading was excavated over the reporting period, giving a total length of 1545.3m of Main Tunnel Top Heading excavated to date.

Face No.7 - 148.8m of Top Heading excavated from St. 1+396.5 to St. 1+545.3

Bench excavation

- 105.25m of bench excavated from St. 0+441.4 to St. 0+546.65, 72.45m from St. 0+619.1 to St. 0+546.65 and 64.7m from St. 0+710 to St. 0+774.7 (West side).

- 111m of bench excavated from St. 0+425 to St. 0+536, 73.55m from St. 0+609.55 to St. 0+536, 54m from St. 0+710 to St. 0+764 and 16.7m from St. 1+097 to St. 1+080.3 (East side).

Concrete

Concrete for Foundation Beam -247m Fr. St. 0+280 to St. 0+527 West Side

Concrete for Foundation Beam -259.4m Fr. St. 0+282.6 to St. 0+542 East Side. Quantity: 240m3

Concrete for Tunnel Lining of of 120m from St. 7+865.825 to St. 7+745.825
Quantity: 1354m3

Lining: Installation of Mole Drain: 210m

    Installation of Waterproofing Membrane: 196m of Tunnel

  • Access road to Water Reservoir

Completed 80m of drainage ditch and 1 No. Culvert.

  • Bridge No. 1

Excavation for the South Abutment: 100 m3

Major Events and Issues

 

Activities for Coming Month

  • Access Road to Water Reservoir

Construction drain: 50m

  • Bridge No. 1

Placement of concrete for Bridge Abutment: 70m3

  • Tunnel Excavation

Excavation of Evacuation Tunnel: 140m from St. 1+622.2 to St. 1+762.2

Excavation of Face 7 of Main Tunnel : 140m from Km 1+545.3 to Km 1+685.3

Excavation and support of bench:250m from Km 0+725.2 to Km 0+875.2

Concrete placement for Tunnel Foundation: 200m3

Placement of concrete lining: 156m - 13 blocks

Installation of waterproofing membrane: 132m

Installation of Mole Drain: 100m

  • Other Works

Placement of foundation concrete beam, drainpipe and cover of rockbolt heads.

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination