Progress Report > Package IB - South Tunnel Section
During the reporting period 150.5m of Evacuation Tunnel and 162.8m of Main Tunnel Top Heading was excavated, giving a total length of 1507.5m of Evacuation Tunnel and 1396.5m of Main Tunnel Top Heading excavated to date. Bench excavation continued with 320.42m being excavated on the West Side and 200.82m excavated on the East Side. Tunnel lining commenced with 48m of tunnel completed. Excavation is advancing well and compared to the original schedule shows the Main Tunnel being four weeks behind programme and the Evacuation Tunnel ten weeks. At current rates excavation should be back on programme by early 2003. Tunnel Lining commenced late, but three pours were completed within a one week period, proving the contractor can hit the required progress rate. A
fatal accident occurred on the 31st October 2002 whilst
permanent steel ribs were being erected for the tunnel lining.
A total of 150.5m of Evacuation Tunnel was excavated from St. 1+357 to St 1+507.5 over the reporting period. Giving a total length of 1507.5m of tunnel excavated to date. The items carried out during the month can be quantified as follows:
A total of 162.8m of Main Tunnel Top Heading was excavated over the reporting period, giving a total length of 1396.5m of Main Tunnel Top Heading excavated to date. Face No.7 - 162.8m of Top Heading excavated from St. 1+233.7 to St. 1+396.5 Bench excavation
Face No. 7: Excavation of 162.8m of Top Heading
Completed 30m of road pavement and 150m of drainage ditch and 1 No. Culvert.
Excavation for the South Abutment: 1000 m3 Concrete poured for North Abutment: 185.5 m3 Major Events and Issues
Activities for Coming Month
Construction drain: 50m Construction culvert No. 1: Complete
Excavation of abutment foundation: 500m3 Placement of concrete for Bridge Abutment: 180m3
Excavation of Evacuation Tunnel: 100m from St. 1+507.5 to St. 1+607.5 Excavation of Cross Passage No. 9 Excavation of Face 7 of Main Tunnel : 140m from Km 1+396.5 to Km 1+536.5 Excavation and support of bench: 200m from Km 0+425 to Km 0+625 Concrete placement for Tunnel Foundation: 200m3 Placement of concrete lining: 120m - 10 blocks Installation of waterproofing membrane: 132m Installation of Mole Drain: 150m
Placement of foundation concrete beam, drainpipe and cover of rockbolt heads. This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||||||||