As of October 31, 2002

Physical Progress

Contractor

JV of Dong Ah and Song Da

Commencement of the Works

1st October 2000

Time Elapsed (days) 759 of 1460 (51.98%)

Progress

Main Tunnel(2417m)

+162.8m - 1396.5m (57.78%)

Evacuation Tunnel(2429m)

+150.5m - 1507.5m (62.06%)

Access Road to Water Reservoir.

Completed 50m of road pavement and 150m of drainage ditch

Bridge No.1(58m)

Excavation for North Abutment: 1500m3

Concrete poured for pier: 200m3

Others

 

Photographs

South Tunnel Portal
Drilling for Blasting of Bench
Mucking at Face No.7
Covering head of rockbolts by mortar
Cutting Head of Rockbolts
Covering head of rockbolts by geotextile
Installation of Waterproofing Membrane
Installation of Steel Bars for Block No.2 - Main Tunnel Concrete Lining
Installation of Steel Rib for Concrete Lining
Placement of Concrete for Lining of Main Tunnel
Fixing of Geotextile for Lining of Main Tunnel
Placement of Concrete for Foundation Beam
Construction of Evacuation Tunnel
Installation of Steel Bars for North Abutment
Construction of North Abutment

Top

Construction Supervision

Summary

During the reporting period 150.5m of Evacuation Tunnel and 162.8m of Main Tunnel Top Heading was excavated, giving a total length of 1507.5m of Evacuation Tunnel and 1396.5m of Main Tunnel Top Heading excavated to date.

Bench excavation continued with 320.42m being excavated on the West Side and 200.82m excavated on the East Side.

Tunnel lining commenced with 48m of tunnel completed.

Excavation is advancing well and compared to the original schedule shows the Main Tunnel being four weeks behind programme and the Evacuation Tunnel ten weeks. At current rates excavation should be back on programme by early 2003.

Tunnel Lining commenced late, but three pours were completed within a one week period, proving the contractor can hit the required progress rate.

A fatal accident occurred on the 31st October 2002 whilst permanent steel ribs were being erected for the tunnel lining.

  • Evacuation Tunnel

A total of 150.5m of Evacuation Tunnel was excavated from St. 1+357 to St 1+507.5 over the reporting period. Giving a total length of 1507.5m of tunnel excavated to date. The items carried out during the month can be quantified as follows:

Blasting: 9830 kg

Shotcrete 50mm thickness:  1627.5 m2

  • Main Tunnel

A total of 162.8m of Main Tunnel Top Heading was excavated over the reporting period, giving a total length of 1396.5m of Main Tunnel Top Heading excavated to date.

Face No.7 - 162.8m of Top Heading excavated from St. 1+233.7 to St. 1+396.5

Bench excavation

- 229.52m of bench excavated from St. 0+211.88 to St. 0+441.4 and 90.9m from St. 0+710 to St. 0+619.1 (West side)

- 100.37m of bench excavated from St. 0+324.63 to St. 0+425 and 100.45m from St. 0+710 to ST. 0+609.55 (East side)


The items carried out during the month can be quantified as follows:

Face No. 7: Excavation of 162.8m of Top Heading

Blasting: 23424 kg

Shotcrete 50mm thickness: 3483.6 m2

SN rockbolt 3m: 11 pcs

SN rockbolts 4m: 114 pcs

Bench Excavation

Blasting 5251 kg

Installation of wire mesh CQS6 two layer 43.2m2

Shotcrete for temporary support 50mm 1544.26m2

SN rockbolt 3m 50 pcs

SN rockbolt 4m 25 pcs

Concrete

Concrete for Foundation Beam -155.5m Fr. St 0+124.5 to 0+280 West Side

Concrete for Foundation Beam -134.2m Fr. St 0+148.4 to 0+282.6 East Side
Quantity: 200m3

Concrete for Tunnel Lining of 47.929m from St. 7+913.754 to St. 7+865.825
Quantity: 589m3

Lining: Installation of Mole Drain: 68m

    Installation of Waterproofing Membrane: 62m of Tunnel

  • Access road to Water Reservoir

Completed 30m of road pavement and 150m of drainage ditch and 1 No. Culvert.

  • Bridge No. 1

Excavation for the South Abutment: 1000 m3

Concrete poured for North Abutment: 185.5 m3

Major Events and Issues

 

Activities for Coming Month

  • Access Road to Water Reservoir

Construction drain: 50m

Construction culvert No. 1: Complete

  • Bridge No. 1

Excavation of abutment foundation: 500m3

Placement of concrete for Bridge Abutment: 180m3

  • Tunnel Excavation

Excavation of Evacuation Tunnel: 100m from St. 1+507.5 to St. 1+607.5

Excavation of Cross Passage No. 9

Excavation of Face 7 of Main Tunnel : 140m from Km 1+396.5 to Km 1+536.5

Excavation and support of bench: 200m from Km 0+425 to Km 0+625

Concrete placement for Tunnel Foundation: 200m3

Placement of concrete lining: 120m - 10 blocks

Installation of waterproofing membrane: 132m

Installation of Mole Drain: 150m

  • Other Works

Placement of foundation concrete beam, drainpipe and cover of rockbolt heads.

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination