As of September 30, 2002

Physical Progress

Contractor

JV of Dong Ah and Song Da

Commencement of the Works

1st October 2000

Time Elapsed (days) 729 of 1460 (49.9%)

Progress

 

Main Tunnel(2417m)

+149.8m - 1233.7m (51.04%)

Evacuation Tunnel(2429m)

+152.8m - 1357.0m (55.87%)

Access Road to Water Reservoir.

Completed 50m of road pavement and 150m of drainage ditch

Bridge No.1(58m)

Excavation for North Abutment: 1500m3

Concrete poured for pier: 200m3

Others

 

 

Photographs

South Portal
Installation of steel bars for block No. 1 of concrete lining
Installation of steel bars for block No. 1 of concrete lining
Preparation for placement of concrete block No. 1
Movement of shutter to location for placement of concrete
Placement of concrete for concreet block No. 1 of tunnel lining
Excavation of bench
Construction of Face No. 7 of Main Tunnel
Repair steel rib of Main Tunnel
Placement of concrete for foundation beam
Construction of Evacuation Tunnel
Excavation of North Abutment of Birdge No. 1
Excavation of North Abutment of Birdge No. 1
Excavation of West Slope
Access road to Water reservoir

 

Top

Construction Supervision

Summary

During the reporting period 152.8m of Evacuation Tunnel and 149.8m of Main Tunnel Top Heading was excavated, giving a total length of 1357m of Evacuation Tunnel and 1233.7m of Main Tunnel Top Heading excavated to date.

The soft ground invert was completed and work commenced with the bench excavation from St. 0+100.

The erection of the concrete lining form was completed and the first pour of the cut and cover portal section carried out.

Overall excavation is advancing well and compared to the original schedule shows the Main Tunnel being five weeks behind programme and the Evacuation Tunnel ten weeks. At current rates excavation should be back on programme by early 2003.

Tunnel Lining will now commence in mid-October, there will be a delay in the start date due to the late delivery of waterproof membrane from Italy.

  • Evacuation Tunnel

A total of 152.8m of Evacuation Tunnel was excavated from St. 1+204.2 to St 1+357 over the reporting period. Giving a total length of 1357m of tunnel excavated to date. The items carried out during the month can be quantified as follows:

Blasting: 9775 kg

Shotcrete 50mm thickness:  1632.4 m2

  • Vehicle cross passage at St. 1+097.825

The vehicle cross passage was excavated a total length of 21.5m from the Evacuation Tunnel. The items carried out during the month can be quantified as follows:

Blasting: 2526 kg

Shotcrete for temporary support 50mm thick: 239m2

SN rockbolts 2 m long: 2 pieces

SN rockbolts 4m long: 4 pieces

  • Main Tunnel

A total of 149.8m of Main Tunnel Top Heading was excavated over the reporting period, giving a total length of 1233.7m of Main Tunnel Top Heading excavated to date.

Face No.7 – 149.8m of Top Heading excavated from St. 1+083.9 to St. 1+233.7

Face No. 1 Invert – 17m of invert excavated from St. 0+083 to St. 0+100

Bench excavation – 43 of bench excavated from St. 0+143 to St. 0+100

– 39.88m of bench excavated from St. 0+172 to St. 0+211.88 (West side)

– 152.63m of bench excavated from St. 0+172 to St. 0+324.63 (East side)

The items carried out during the month can be quantified as follows:

Face No. 7: Excavation of 149.8m of Top Heading

Blasting:   21135 kg

Shotcrete 50mm thickness: 3160.36 m2

SN rockbolts 4m:  108 pcs

Invert of Face No.1: Excavation of 17 of invert

Blasting: 147kg

Concrete backfill for Invert Type D                 392m3

Installation of steel ribs 150x150                21370.4 kg

Installation of wire mesh CQS6 two layer          489m        

Shotcrete for temporary support 150mm            190.24m2

SN rockbolt 4m                                         68 pcs

SN rockbolt 6m                                         32 pcs

Bench Excavation

Blasting                                              2318 kg

Installation of steel ribs 125x125                5776.72 kg

Installation of wire mesh CQS6 two layer          418.5m     

Shotcrete for temporary support 125mm          529.58m2

 SN rockbolt 3m                                  135 pcs

SN rockbolt 4m                                  12 pcs

Concrete

Concrete 21m of Invert from St. 0+079 to St. 0+100. Quantity  392m3

Concrete 57.5m of Foundation Beam of 57.5m from St. 0+067 to 0+124.5 West Side

Concrete 84.4m of Foundation Beam of 84.4m from St. 0+067 to 0+148.4 East Side. Quantity     55.5m3

Concrete for Cut and Cover Portal from St. 7+923.41 to St. 7+913.754. Quantity       152m3

  • Excavation of West Slope

Excavation for bench No. 3 and No. 4  500m3

Construction of drainage ditch at the bottom of the slopes   120m

  • Access road to Water Reservoir

Completed 50m of road pavement and 150m of drainage ditch.

  • Bridge No. 1

Excavation for North Abutment: 1500 m3

Concrete poured for pier: 200 m3

Major Events and Issues

- Completion of excavation and support of West Slopes

- Completion of concrete placement for access road to water reservoir

- Carrying out the installation of waterproofing membrane

Activities for Coming Month

  • Access Road to Water Reservoir

Construction of concrete pavement:                     30m

Construction drain:                               200m

  • Bridge No. 1

Placement of concrete for Bridge Abutment:            200m3

  • Tunnel Excavation

Excavation of Evacuation Tunnel: 120m from St. 1+357 to St. 1+477

Excavation of Face No. 7 of Main Tunnel: 140m from St. 1+233.7 to St. 1+373.7

Excavation and support of : 200m from St. 0+211.8 to St. 0+411.8

Concrete placement for Tunnel Foundation : 200m3

Placement of concrete lining: 48m – 5 blocks

Installation of waterproofing membrane: 60m (according to length of tunnel)
  • South Tunnel Portal

Excavation and support of West Slope: Completion

  • Other Works

Placement of foundation concrete beam, drainpipe and cover of rockbolt heads.

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination