Bridge
No.2
North abutment, Pier 1, Pier 2 and Pier 3 have
been completed of concrete works up to cross head.
Pier 4, Pier 5, Pier 6, Pier 7, Pier 8, Pier 9
and South abutment are under construction.
4 nos. of girder are finished production at casting
yard near by north abutment.
2 nos. of girders are launched at span 1.
Bridge
No.3
Site preparation work has started.
Bridge
No.4
North abutment, Pier 1', Pier 1, Pier 3, Pier
4, Pier 5 and south abutment have been completed
of concrete works.
Pier No.2 is under construction.
Span No.6 and No.7 are finished launching and
1st stage of slab concrete.
18 nos. of PCI girders are finished production
and continue.
Bridge
No.5
North abutment, Pier 1, Pier 2 and South abutment
have been completed of concrete works.
Pier 3 is under construction.
1 no. of PCI girders is finished production and
continue.
Bridge
No.6
North abutment, Pier 1 and Pier 2 have been completed
of concrete works.
Pier 3, Pier 4 and South abutment are under construction.
Bridge
No.7
North abutment, Pier 3, and South abutment have
been completed of concrete works.
Pier 1 and Pier 2 are under construction.
1 no. of PCI girders is finished production and
continue.