As of September 30, 2002

Physical Progress

Contractor

JV of Cienco, Lung Lo and Vinawaco

Commencement of the Works

26 July 2001

Time Elapsed (days) 400 of 960 (41.6%)
Progress  
Bridge No.2 (334m) North Abutment, P1, P2 & P3 completed.P4 ~ P9 & South Abutment under cosntruction.
Bridge No.3 (33m) Site preparation work started
Bridge No.4 (175m)

Excavation Work: 8 foundations completed.Concrete work: A1, P1, P3, P5 & A2 completed. P2 under construction. Lauching work is carried out for span b/t P6 & P7

Bridge No.5 (133m)

Concrete work: A1, P1, P2 & A2 completed. P3 under construction

Bridge No.6 (150m)

Concrete work: A1, P1 & P2 completed, P3, P4 & A2 under construction.

Bridge No.7 (133m)

Concrete work: A2, P1 & P2 completted, A1, P3, P4 under construction.

Temporary Work Temporary Access Road Network nearly completed the road bed.

Photographs

Road section Sta. 11+440
Road section Sta. 11+660
Pier 5 of Bridge No.2 under construction
Overview of Bridge No.2
Foundation of Abutment A2 - Bridge 3 under excavation
Girder casting yard of Bridge No. 4
Overview of Bridge No.4 from Abutment A2
Overview of Bridge No.5
Girder casting yard of Bridge No. 5
Overview of Bridge No.6
Overview of Bridge No.7
Formwork of GN 7-3 and Girder casting yard of Bridge No. 7
Underpass Culvert (4x4.3m) - Km 11+260
Box Culvert at Km 9+115

Top

Construction Supervision

Summary

Bridge No.2
North abutment, Pier 1, Pier 2, Pier 3 and Pier 4 have been completed of concrete works up to cross head.

Pier 4, Pier 5, Pier 6, Pier 7, Pier 8, Pier 9 and South abutment are under construction.

7 nos. of girder are finished production ar casting yard near by North abutment.

Lauching for Span 1 has been completed.

Bridge No.3
Site preparation work has started.

Bridge No.4
All sub-structures has completed for concrete work.

Span No.5, No.6 and No.7 were finished lauching and 1st stage of slab concrete.

21 nos. of PCI girders are finished production and continued

Bridge No.5
All sub-structures were completed for concrete work.

3 nos. of PCI girders are finished production and will be continued

Bridge No.6

All sub-structures has completed for concrete work.

Preparation work for PCI girder production has commenced

Bridge No.7
North abutment, Pier 3, and South abutment have been completed of concrete works.
Pier 1 and Pier 2 are under construction.
1 no. of PCI girders is finished production and continue.

Permanent Works

  • Bridge No. 2:

Substructure:

North abutment has been completed of concrete works.

Pier No.1 has been completed of concrete works up to cross head.

Pier No.2 has been completed of concrete works up to cross head.

Pier No.3 is under construction of concrete works.

Pier No.4 is under construction of concrete works.

Pier No.5 is underconstruction of concrete works.

Pier No.6 is under construction of concrete works.

Pier No.7 is under construction of concrete works.

Pier No.8 is under construction of concrete works.

Pier No.9 has started excavation.

South abutment has started excavation.

Superstructure

Launching work has commenced at span 1 and 2 nos. of girder are launched.

Girder Production

4 nos. of girder have been produced at casting yard near by north abutment.

  • Bridge No.3: Site preparation work has started this month
  • Bridge No.4:

Substructure:

North abutment has been completed concrete works.

Pier No.1' has been completed concrete works up to cross head.

Pier No.1 has been completed concrete works up to cross head.

Pier No.2 is under construction of concrete works.

Pier No.3 is under construction of concrete works up to cross head.

Pier No.4 has been completed of concrete works up to cross head.

Pier No.5 has been completed of concrete works up to cross head.

South abutment has been completed of concrete works.

Superstructure

Span No.6 and No.7 between P-4 and A-2 has been finished launching of girder 10 nos. and 1st stage of superstructure such as diaphragm and deck slab 1st lift.

Girder Production

18 nos. of 35 girders are finished production at girder production yard behind of A-2.

  • Bridge No.5:

Substructure

North abutment has been completed of concrete works.

Pier No.1 has been completed of concrete works up to cross head.

Pier No.2 has been completed of concrete works up to cross head.

Pier No.3 is under construction of concrete works.

South abutment is under construction of concrete works.

Superstructure

Superstructure is not commenced yet.

Girder Production

1 no. of 20 girders is finished production at girder production yard.

  • Bridge No.6:

Substructure

North abutment has been completed of concrete works.

Pier No.1 has been completed of concrete works up to cross head.

Pier No.2 has been completed of concrete works up to cross head.

Pier No.3 is under construction of concrete works.

Pier No.4 is under construction of concrete works.

South abutment is under construction of concrete works.

Superstructure: Superstructure is not commenced yet.

Girder Production: Preparation work has commenced.

  • Bridge No.7:

Substructure

North abutment has been completed of concrete works.

Pier No.1 is under construction of concrete works.

Pier No.2 is under construction of concrete works.

Pier No.3 has been completed of concrete works up to cross head.

South abutment has been completed of concrete works.

Superstructure: Superstructure is not commenced yet.

Girder Production: 1 no. of 25 girders is finished production at girder production yard.

  • Road Works:

    Earthworks

    Excavation work is under construction.

    Embankment of toll plaza area is under constructing.

  • Schedule Overview:

Critical path is running on the schedule of bridge No.2 and it seems to be difficult to achieve completion time. Girder production schedule and sequence of superstructure may be necessary to review.

Earthwork of road works is also going to be delay. Contractor was requested to review equipment schedule and detail schedule of sub-base.

Earthwork area 3 is not enough the rate of progress because of delaying box culvert.

Activities for Coming Months

  • Permanent Work

Bridge No.2:

Bridge No.3:

Bridge No.4:

Bridge No.5:

Bridge No.6:

Bridge No.7:

Road section:

Top

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination