Bridge
No.2
North abutment, Pier 1, Pier 2, Pier 3 and Pier
4 have been completed of concrete works up to
cross head.
Pier
4, Pier 5, Pier 6, Pier 7, Pier 8, Pier 9 and
South abutment are under construction.
7
nos. of girder are finished production ar casting
yard near by North abutment.
Lauching
for Span 1 has been completed.
Bridge
No.3
Site preparation work has started.
Bridge
No.4
All sub-structures has completed for concrete
work.
Span
No.5, No.6 and No.7 were finished lauching and
1st stage of slab concrete.
21
nos. of PCI girders are finished production and
continued
Bridge
No.5
All sub-structures were completed for concrete
work.
3
nos. of PCI girders are finished
production and will be continued
Bridge
No.6
All
sub-structures has completed for concrete work.
Preparation
work for PCI
girder production has commenced
Bridge
No.7
North abutment, Pier 3, and South abutment have
been completed of concrete works.
Pier 1 and Pier 2 are under construction.
1 no. of PCI girders is finished production and
continue.