North
abutment has been completed of concrete works.
Pier
No.1 has been completed of concrete works up
to cross head.
Pier
No.2 has been completed of concrete works up
to cross head.
Pier
No.3 has been completed of concrete works up
to cross head.
Pier
No.4 is under construction of concrete works
Pier
No.5 is under construction of concrete works
Pier
No.6 is under construction of concrete works.
Pier
No.7 is under construction of concrete works
Pier
No.8 is under construction of concrete works.
Pier
No.9 has started excavation.
South
abutment has started excavation.