As of October 31, 2002

Physical Progress

Contractor

JV of Cienco, Lung Lo and Vinawaco

Commencement of the Works

26 July 2001

Time Elapsed (days) 430 of 960 (44.79%)
Progress
Bridge No.2 (334m) Concrete work for north abutment, P1, 2, 3 completed.P4, 5, 6, 7, 8, 9 and south abutment under construction. Lauching for Span 1 completed.
Bridge No.3 (33m) Footing of south abutment has completed
Bridge No.4 (175m)

Concrete work for all substructure completed. Span No.4, 5, 6, 7 finished lauching and 1st stage of slab concrete.

Bridge No.5 (133m)

Concrete work for all substructure completed.

Bridge No.6 (150m)

Concrete work for all substructure completed. Preparation work for PCI girder production commenced.

Bridge No.7 (133m)

Concrete work for all substructure completed. 6 nos of PCI girder completed.

Temporary Work Under construction

Photographs

Girder Launching System of Bridge No.2
Overview of Bridge No.2
Abutment A2 of Bridge No.3 Under Construction
Girder Casting Yard of Bridge No.4
Deck Slab of Spans A2-P5; P5-P4; P4-P3; P3-P2 of Bridge No.4
The Fifth Span (P2-P1) of Bridge No.4 Under Launching Girder
Girder Casting Yard of Bridge No.5
Overview of Bridge No.5
Girder Casting Yard of Bridge No.7
Overview of Bridge No.7
Road Work Sta. 11+360 - 11+440
The First 400m of Connection Road to NH1 (From Km. 0+764.97 to 1+185.09)
Underpass Culvert at Km. 9+115
Underpass Culvert (4 x 4.3) at Km. 11+260

 

Top

Construction Supervision

Permanent Works

  • Bridge No. 2:

Substructure:

North abutment has been completed of concrete works.

Pier No.1 has been completed of concrete works up to cross head.

Pier No.2 has been completed of concrete works up to cross head.

Pier No.3 has been completed of concrete works up to cross head.

Pier No.4 is under construction of concrete works

Pier No.5 is under construction of concrete works

Pier No.6 is under construction of concrete works.

Pier No.7 is under construction of concrete works

Pier No.8 is under construction of concrete works.

Pier No.9 has started excavation.

South abutment has started excavation.

Superstructure

Span 1 has finished slab concrete and to continue to span 2.

Girder Production

10 nos. of girder have been produced at casting yard near by north abutment.

  • Bridge No.3: Footing of south abutment has completed and to continue elevation
  • Bridge No.4:

Substructure:

All sub-structure has been completed for concrete work

Superstructure

Span No.4, No5, No.6 and No.7 between P-2 and A-2 has been finished launching of girder 20 nos. and 1st stage of superstructure such as diaphragm and deck slab 1st lift.

Girder Production

27 nos. of 35 girders are finished production at girder production yard behind of A-2.

  • Bridge No.5:

Substructure

All sub-structure has been completed for concrete work

Superstructure

Superstructure is not commenced yet.

Girder Production

5 no. of 20 girders is finished production at girder production yard.

  • Bridge No.6:

Substructure

All sub-structure has been completed for concrete work

Superstructure: Superstructure is not commenced yet.

Girder Production: Preparation work has commenced.

  • Bridge No.7:

Substructure

North abutment has been completed of concrete works.

Pier No.1 is under construction of concrete works up to cross head.

Pier No.2 is under construction of concrete works up to cross head.

Pier No.3 has been completed of concrete works up to cross head.

South abutment has been completed of concrete works.

Superstructure: Superstructure is not commenced yet.

Girder Production: 6 no. of 25 girders is finished production at girder production yard.

  • Road Works:

    Earthworks

    Excavation work is under construction and 80,000m3 of 124,400m3 has completed.

    Embankment of toll plaza area is under constructing and 23,500m3 of 60,600m3 has completed.

  • Schedule Overview:

Critical path is running on the schedule of bridge No.2 and it seems to be difficult to achieve completion time. Girder production schedule and sequence of superstructure may be necessary to review.

Earthwork of road works is also going to be delay. Contractor was requested to review equipment schedule and detail schedule of sub-base.

Earthwork area 3 is not enough the rate of progress because of delaying box culvert.

Activities for Coming Months

  • Permanent Work

Bridge No.2:

Bridge No.3:

Bridge No.4:

Bridge No.5:

Bridge No.6:

Bridge No.7:

Road section:

Top

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination