Welcome to Our Site!
 

 

As of July 31, 2002

Physical Progress

Contractor

JV of Cienco, Lung Lo and Vinawaco

Commencement of the Works

26 July 2001

Time Elapsed (days) 340 of 960 (35.4%)
Progress  
Bridge No.2 (334m) North Abutment, P1, P2 & P3 completed.P4 ~ P9 & South Abutment under cosntruction.
Bridge No.3 (33m) Site preparation work started
Bridge No.4 (175m)

Excavation Work: 8 foundations completed.Concrete work: A1, P1, P3, P5 & A2 completed. P2 under construction.Lauching work is carried out for second span b/t P4 & P5

Bridge No.5 (133m)

Excavation Work: all foundation completedA1, P1 & P2 completed. P3, A2 under construction (80%)

Bridge No.6 (150m)

Excavation work of all foundation completed.Concrete work: A1, P1 & P2 completed, P2~P4 under construction.

Bridge No.7 (133m)

Excavation work: 5 foundations completed.Concrete work: A2 completted, A1, P1~P3 under construction.

Temporary Work Temporary Access Road Network nearly completed the road bed.

 

Photographs

Pier 6, Pier 7 of Bridge No. 2
Gider Lauching System of Birge No. 2
Girder Casting Yard of Bridge No. 4
Overview of A2-P5 Span - Bridge No. 4
Overview of Bridge No. 6
The first Gider casted of Birgde No. 5
Overview of Birgde No. 6
Girder casting yard of Bridge No. 6
Overview of Bridge No. 7
Formwork of the first Girder of Bridge No.7
Box Culvert Km. 9+115 under construction

 

Top

Construction Supervision

Summary

  • Bridge No. 2:

Substructure:

North abutment has been completed of concrete works.

Pier No.1 has been completed of concrete works up to cross head.

Pier No.2 has been completed of concrete works up to cross head.

Pier No.3 is under construction of concrete works up to cross head.

Pier No.4 is under construction of concrete works.

Pier No.5 is under excavation.

Pier No.6 is under construction of concrete works.

Pier No.7 is under construction of concrete works.

Pier No.8 is under construction of concrete works.

Pier No.9 has started excavation.

South abutment has started excavation.

Superstructure

Superstructure is not commenced yet.

Girder Production

2 nos. of girder has been produced at casting yard near by north abutment.

  • Bridge No.3: Site preparation work has started this month
  • Bridge No.4:

Substructure:

North abutment has been completed concrete works.

Pier No.1' has been completed concrete works up to cross head.

Pier No.1 has been completed concrete works up to cross head.

Pier No.2 is under construction of concrete works.

Pier No.3 is under construction of concrete works.

Pier No.4 has been completed of concrete works up to cross head.

Pier No.5 has been completed of concrete works up to cross head.

South abutment has been completed of concrete works.

Superstructure

Span No.7 between P-5 and A-2 has been finished launching of girder 5 nos. and under construction of diaphragm.

Girder Production

14 nos. of 35 girders are completed production at girder production yard behind of A-2.

  • Bridge No.5:

Substructure

North abutment has been completed of concrete works.

Pier No.1 has been completed of concrete works up to cross head.

Pier No.2 has been completed of concrete works up to cross head.

Pier No.3 is under construction of concrete works.

South abutment is under construction of concrete works.

Superstructure

Superstructure is not commenced yet.

Girder Production

1 no. of 20 girders is finished production at girder production yard.

  • Bridge No.6:

Substructure

North abutment has been completed of concrete works.

Pier No.1 has been completed of concrete works up to cross head.

Pier No.2 has been completed of concrete works up to cross head.

Pier No.3 is under construction of concrete works.

South abutment is under construction of concrete works.

Superstructure: Superstructure is not commenced yet.

Girder Production: No activities for this area at this moment.

  • Bridge No.7:

Substructure

North abutment has been completed of concrete works.

Pier No.1 is under construction of concrete works.

Pier No.2 is under construction of concrete works.

Pier No.3 has been completed of concrete works up to cross head.

South abutment has been completed of concrete works.

Superstructure: Superstructure is not commenced yet.

Girder Production: Preparation works has commenced.

  • Road Works:

    Earthworks

    Excavation work is under construction.

    Embankment of toll plaza area is under constructing.

  • Schedule Overview:

Critical path is running on the schedule of bridge No.2 and it seems to be difficult to achieve completion time. Girder production schedule and sequence of superstructure may be necessary to review.

Earthwork of road works is also going to be delay. Contractor was requested to review equipment schedule and detail schedule of sub-base.

Earth work area 3 is not enough the rate of progress because of delaying box culvert.

Activities for Coming Months

  • Permanent Work

Bridge No.2:

Bridge No.3:

Bridge No.4:

Bridge No.5:

Bridge No.6:

Bridge No.7:

Road section:

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination