As of November 30, 2002

Physical Progress

Contractor

JV of Hazama and Cienco 6

Commencement of the Works

1st October 2000

Time Elapsed (days) 788 of 1460 (53.97%)

Progress

Main Tunnel(3857m)

+ 67.30m - 1,904.40m (49.38%)

Evacuation Tunnel(3857m)

+ 124.2m - 1,925.50m (49.92%)

Ventilation Tunnel(1810m)

+ 97.90m - 1,593.51m (84.02%)

Others

 

Photographs

North portal
Ventilation Adit Portal
Main Tunnel - Face drilling
Main Tunnel - Loading of explosive
Main Tunnel - Mucking
Main Tunnel - Shotcrete spraying
Rear works - Compacting the base for foundation beam 
Rear works - Mole drain pipe installation for tunnel drainage
Rear works - Rockbolt head cover before installatio of waterproofing membrane
Rear works - concrete pouring for tunnel concrete lining
Joint site inspection of geological overbreaks
Niche excavation by breaker
Installation of revesion shaft and form setting for concrete
Unforeseen deformation at main tunnel
Unforeseen deformation at main tunnel
Unforeseen deformation at main tunnel
Unforeseen deformation at main tunnel
Fault lines and crushing zone occurred bid cave-in on crown part at Main tunnel Sta 3+511 to 1+516
Fault lines and crushing zone completely the cutting face at Main tunnel Sta 3+521.5 (round no. 650)
Unforeseen rock deformation at right side walls Main tunnel Sta 3+483.75 to 3+500.25, additional IBO rockbolts, wiremesh & shotcrete t=5cm
Installation of additional rockbolts at same station
Concreting works for layby right No. 1 segment No 2-1 at Main Tunnel Sta 2+384.5 to 2_396.4
Evacuation Tunnel - Face drilling
Evacuation Tunnel - loading of explosive
Evacuation Tunnel - Deposing the excavated materials to temp. stock area
Evacuation Tunnel - shotcrete spraying
Evacuation Tunnel - slicken side & some joint on the crown part appear from end of this month Sta 3+547.4
Layby right No.1 segment 2-1 to 2-3 including Pedestrian C.P No.2 connection
Ventilation Adit - Face drilling
Ventilation Adit - Loading of explosive
Ventilation Adit - Mucking
Ventilation Adit - Shotcrete spraying
Ventilation Adit - Goog rock condition class B~A
Safety meeting

 

Top

Construction Supervision

Summary

As of November 25, 2002, total length of Main Tunnel Excavation has reached to Sta. 3+540.2 or 1,887.2 meters (including four (4) laybys) from the Tunnel Portal.

During this month, very bad geological condition with unforeseen deformation is experiencing during the excavation of the Main Tunnel. As per instruction from the Engineer, Rock Support Types were changed from Rock Support Type I to II and III, rough length was shortened to less than 2m and also many additional supporting systems were installed to control and overcome the deformation.

Thirty-six (36) niches (9 emergency & call niche and 27 firefighting niches) were completely excavated inside the main tunnel.

Concerning of the foundation beam and concrete lining works at the main tunnel were carried out. As of November 25, 2002, concrete lining construction has reached to Sta. 3+546.5 or 1,893.5 meters from the tunnel portal.

Four (4) Cross Passageways were completely excavated across the evacuation and main tunnels. An approved additional cross passage was also excavated concerning the main and evacuation tunnel.

As of November 25, 2002, total length of ventilation adit excavation reached to sta. 0+175.6 or 1,573.9 meters from the Tunnel Portal.

 

Major Events and Issue

Site Inspection by TCQM

On November 21, 2002, TCQM delegation made inspected the Project.

Monthly Meeting

On November 20, 2002, Monthly Meeting between the Employer, the Engineer and the Contractor was held at the Employer’s/Engineer’s North Office.

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination