As of December 31, 2002

Physical Progress

Contractor

JV of Hazama and Cienco 6

Commencement of the Works

1st October 2000

Time Elapsed (days) 818 of 1460 (56.03%) Remaining 642 days

Progress

 

Main Tunnel(3857m)

+ 95.70m - 2000.10m (51.86%)

Evacuation Tunnel(3857m)

73.40m - 1,998.70m (51.82%)

Ventilation Tunnel(1810m)

+ 111.80m - 1,705.31m (89.92%)

Others  

 

Photographsa

North Portal
Ventilation Adit Portal
Mucking at the Main Tunnel
Loading of Explosive at Main Tunnel
Main Tunnel Concrete Lining Concrete Pouring
Installation of Waterproofing Membrane
Excavation for Foundation Base
Form Setting of Niche
Joint Site Inspection of Geological Overbreaks
Concrete Samples from Concrete Lining For Quality Control Test
Wiremesh Installation at Left hand Side Main Tunnel at Station 3+604.1
Cleaning/Washing Water with Aircompressor up to the Rock Surface prior to Lean/Leveling Concrete for Foundation Beam at main Tunnel Station 3+127.5
Face Drilling At Evacuation Tunnel
Shotcrete Spraying at Evacuation Tunnel
Fracture & Some Joint at Evacuation Tunnel Station 3+639.5
Face Drilling at Ventilation Adit
Dewatering Inside Tunnel at Ventilation Adit
Steel Fiber Shotcrete Pull-out Test After 2 Hours (Trial Shotcreting On-Site)
Steel Fiber Shotcrete Flexural Test After 7 days (Trial Mix Design)

 

Top

Construction Supervision

Summary

During this month, the bad geological condition with unforeseen deformation reported last month is still experienced during the excavation of the Main Tunnel.

Thirty-eight (38) niches (9 emergency & call niche and 29 firefighting niches) were completely excavated inside the main tunnel

Concreting of the foundation beam and concrete lining works at the main tunnel were carried out. As of December 25, 2002, conrete lining construction has reached to 1,338.5m.

As of December 25, 2002 total length of Evacuation Tunnel Excavation reached to Sta. 3+628.1 or 1,975.1 meters from the Evacuation Tunnel.

As of December 25, 2002, total length of Ventilation Adit Excavation reached to Sta. 0+67.3 0r 1,682.2 meters from the Tunnel Portal.

 

Major Events and Issue

Site Inspections

On December 18, 2002, Mr. Tran, the General Director of PMU 85 together with the representatives from JBIC, inspected the Project.

On December 22, 2002, Mr. Nguyen Viet Tien, Vice Minister of MOT inspected the Project Site.

Monthly Meeting

On December 20, 2002, Monthly Meeting between the Employer, the Engineer and the Contractor was held at the Employer’s/Engineer’s North Office.

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination