Welcome to Our Site!
 

 

As of September 30, 2002

Physical Progress

Contractor

JV of Hazama and Cienco 6

Commencement of the Works

1st October 2000

Time Elapsed (days) 729 of 1460 (49.9%)

Progress

Main Tunnel(3857m)

+ 141.1m - 1681.8m (43.60%)

Evacuation Tunnel(3857m)

+ 119.5m - 1621.3m (42.03%)

Ventilation Tunnel(1810m)

+ 114.3m - 1392.0m (76.90%)

Others

 

Photographs

North Portal
Ventilation Adit Portal
Setting form (extension from pinolic polywood) for normal section connected to Layby left No.1 at Main Tunnel Segment No. 29 Station 2+015.5 to 2+027.5
Placing concrete for normal section connected to Layby left No.1 at Main Tunnel Segment No. 29 Station 2+015.5 to 2+027.5
Bulkhead/Endform installation for lining comcrete Segment No. 76 at Main Tunnel
Mucking work at Main Tunnel
Shotcrete spraying at Main Tunnel
Setting form and take sample for density test of base of Foundation beam
Set form for foundation beam concrete
Water in-flow from drill hole appeared at Main Tunnel round #568 sta. 3+236.5~239.9
Installation of waterproofing membrane at Main tunnel
Drilling at Ventilation Adit
Charging fo explosive for blasting at Ventilation Adit Tunnel
Rockbolt installation at Ventilation adit
Setting up concrete lining form for tunnel lining concrete
Asphalt pavement construction at access road to Ventilation Adit Portal
Joint inspection on public electrical power monitoring system
Ceremony (1st congress) of Hazama-Cienco6 Labor Union

 

Top

Construction Supervision

Summary

As of September 25, 2002, total length of Main Tunnel excavation has reached to the Sta. 3+291.3 or 1,638.3 meters (including Four (4) Laybys) from the Tunnel Portal.

Thirty-two (32) niches (8 Emergency & Cal Niche and 24 Firefighting niches) were completely  excavated inside the main tunnel.

Concrete work of Foundation Beam and concrete lining works at the main tunnel were carried out. As of September 25, 2002, concrete lining construction has reached to 878.5 meters.

As of September 25, 2002, total length of Evacuation Tunnel Excavation has reached to Sta. 3+239.6 or 1,586.6 meters from the Tunnel Potal.

Four (4) Cross Passageways were completely excavated across the Evacuation and Main Tunnel.

As of September 25, 2002, total length of Ventilation Adit Excavation has reached to Sta. 0+381.1 or 1,368.4 meters from the Tunnel Portal.

Main Tunnel

  • Excavation

In the month of September, fracture zones with water flowing at around 100 liters/min were encountered on crown part for almost two rounds, from station 3+583.5 to 3+590.3. Due to this, the Engineer gave instruction to install pattern rock bolts and increase the shotcrete thickness to 10cm. This geological condition of having joint plane on cutting face and slickenside was observed since August. Geologically, the condition was stable on Class B.

A total length of 131.50m (station 3+186.3 ~ 3+317.8) was excavated in the Main Tunnel this month, giving a total length of 1,681.80m (Progress: 43.60%) from the tunnel portal.

Niche Excavation:

Thirty (33) Niches – Eight (8) Emergency Call Niches and Twenty-Five (25) Firefighting Niches – in the Main Tunnel were already excavated. Excavation of niches continues according to the designed niche distribution plan.

Layby

TThe Layby Left No. 1, 2 and Layby Right No. 1 in the Main Tunnel, which has a total length of thirty-two (32) meters each, were completed as per original plan. The excavation of the Layby Right No. 2 on its original location was also completed, although the location of the Electrostatic Precipitator No.1, which was originally connected to Layby Right No. 2, will be transferred.

  • Behind Works (Behind Tunnel Excavation)

The pouring of Class D concrete for the Foundation Beams of the Lining Concrete continued this month. The placing of concrete continued from Station 2+583.5 to 2+784.5 on both sides with a total length of 201m on each side.

Installation of Mole Drain Pipes, together with filter cement aggregate, on both sides of the tunnel continued simultaneous with the foundation beams.

Cutting of Rock bolt heads and installation of geo-textile covers were continued on areas with random/safety rock bolts.

Installation of EVA Waterproofing Membrane also continued following the covering of random rock bolts. The completed laying/installation of membrane reached to station 2+682.5, totaling a length of 1,018.5m. The Engineer continued to require testing of the welded joint sheets using air pressure test, as per procedure stated on method statement, before continuation of the installation.

Pouring of Concrete Lining also continued as per design segment approved. The Engineer carefully checked, during the joint survey with the contractor, the setting of the form for both bulkhead sides and the thickness as per design requirements.

The Concrete Lining for Standard Section of the Main Tunnel completed until the end of this month totaled to 840 meters. The Lining Concrete were poured using Shutter No. 1 from Segment No. 2 to No. 27 (Sta. 1+665 to Sta. 1+977), Segment No. 30 to No. 58 (Sta. 2+027.5 to Sta. 2+375.5) and from Segment No. 61 to No. 75 (Sta.2+427.5 to Sta.2+607.5). Shutter No.2 was first used on pouring concrete for Segment No. 28 and No. 29 (Sta.1+977 to 1+984.5 and Sta. 2+015.5 to 2+027.5), which connects the standard section of the Main Tunnel to Layby Left No. 1. The completed Concrete Lining includes fifteen (15) Fire Fighting Niches and three (3) Fire Fighting with Emergency Call Niches.

The Concrete Lining of Layby Left No. 1 in Main Tunnel, totaling a length of 31m on station 1+984.5 ~ 2+015.5m, including one (1) Fire Fighting with Emergency Call Niche, was also completed.

The Main Tunnel Concrete Lining completed up to this month totaled to 890.5m (Progress: 23.09%).

For the Pedestrian Cross Passage No.1, only the concrete lining for the block connected to the Main Tunnel, which has a length of 4.1m, was completed.

Evacuation Tunnel

For the Evacuation Tunnel, the rock encountered was in good condition. Generally, the classification of rock was steady on class B and some portion was classified as class A.

The excavated tunnel length for the month of September 2002 was 119.50m (station 3+144.8 ~ 3+264.5), giving a total length of 1,621.30m  (Progress: 42.04%) from the tunnel portal.

This month the excavation of Evacuation Tunnel was shorter due to the excavation of Pedestrian Cross Passage No. 3. This time, the Contractor simultaneously excavated the Cross Passage and Evacuation Tunnel to avoid more delay and to increase the progress, unlike the previous excavation of Cross Passages wherein they totally stopped the excavation of the Evacuation Tunnel.

The Temporary Transformer Niches No. 1~7 were completely excavated as per approved plan submitted by the Contractor. This month, the excavation of temporary niche No.8 was also completed.

The Enlarged Pedestrian Cross Passageway Nos. 1 and 2 was completed. The Pedestrian Cross Passage No. 3 was also completed this month, having the same good rock condition as the Evacuation Tunnel.

The Vehicular Cross Passage No.1 was completely excavated from Evacuation Tunnel and Main Tunnel side with a total length of 19.4m.

Ventilation Adit

Since the beginning of September 2002, fracture zones appeared with water seepage from station 0+471.3 up to station 0+454.3 (03~07 September 2002) and from 0+384.41 up to station 0+364.0 (25~28 September 2002). Therefore, the Engineer issued an instruction to change the supporting system from type I to type II.

The Engineer also instructed the contractor to carry out one-hole exploratory drilling on the cutting face at station 0+467.60m to investigate the rock and water condition ahead. The results of exploratory drilling, which was done in the presence of the Consultant’s Geotechnical Engineer, were: from 0~2m - medium to hard (Class C1 ~ B), 2~4 soft (Class C1), 4~8 - medium hard and no water was encountered along the eight (8) meters length drilled hole. The type II supporting system was changed again to type I at end of this month.

Generally, the rock encountered was classified as class C1 to B this month.

The excavated length for the month of September was 114.30m (station 0+474.8 ~ 0+360.5), totaling to 1,392.01m (Progress: 79.43%) from the tunnel portal.

Problems Encountered – Main, Evacuation and Ventilation Tunnel

This month, the main cause of the delay in the progress of the tunnel excavation may still be attributable to the frequent breakdown of Heavy Equipment, which occurred on almost every shift.

Ventilation Adit - Access Road

Paving of the second layer of 5cm-thick Asphalt to complete the 10cm-thick from submerged area to the connection of the access road with the National Highway No. 1 was done on 1st and 4th of September 2002.

Major Events and Issue

Safety Patrol and Meeting:

On August 26, 2002, the Employer, the Engineer and the Contractors of both South and North Package carried out the Safety Patrol and Meeting.

Organization of Hazama - Cienco6 Labor Union:

Hazama-Cienco6 J.V Labor Union was formally organized last September 10, 2002 and the ceremony was attended by Labor Union officials from Hue Province on September 24, 2002.


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination