Haivan Pass Tunnel CONSTRUCTION PROJECT
Progress Report > Package IA - North Tunnel Section
As of September, 2002 - Home | Next
Water in-flow from drill hole appeared at Main Tunnel round #568 sta. 3+236.5~239.9
Nước ngầm xuất hiện từ lỗ khoan ṿng đào #568 Km. 3+236.5~239.9, hầm chính
Tháng 09/2002 - Trở về | Tiếp This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
Tháng 09/2002 - Trở về | Tiếp
This homepage is presented by the Consultant Team
Any further question should be forwarded to Webmaster or Consultant Team
2005/HVTP Webmaster