At the beginning of August 2002, lean concrete bases for OCC building foundations completed. On August 4, 2002: concrete work of foundation started. On August 17, 2002: all foundation completed, including pillars to bottom of underground beam level -0.250m. Due to the heavy rain, the backfill of the foundations could not start until August 25, 2002. Earthing and perimeter brick works beneath level -0.250m started on August 26, 2002. The
Contractor submitted a master imported list to the Engineer
on August 9, 2002 together with a request for certified
copies of exemption certificates from customs tariffs, import
duties and taxes. Physical Progress in this month
Activities for Coming Months Permanent Works