As of August 31, 2002

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Commencement of the Works

21 December 2001

Time Elapsed (days) 220 of 540 (40.7%)

Progress

 
110/22 kV Substation Foundation works is under construction. Power transformers already manufactured and tested.
110 kV Transmission Line Survey finished. Design for tower & foundation is on progress.

 

Photographs

Concrete work for 110/22kV Substation OCC Building Foundation
Compacting work for backfill for 110/22kV Substation OCC Building
Subface earthing grid work for 110/22kV Substation OCC Building
Brick work for perimeter of 110/22kV Substation OCC Building

 

Top

Construction Supervision

At the beginning of August 2002, lean concrete bases for OCC building foundations completed. On August 4, 2002: concrete work of foundation started. On August 17, 2002: all foundation completed, including pillars to bottom of underground beam level -0.250m. Due to the heavy rain, the backfill of the foundations could not start until August 25, 2002. Earthing and perimeter brick works beneath level -0.250m started on August 26, 2002.

The Contractor submitted a master imported list to the Engineer on August 9, 2002 together with a request for certified copies of exemption certificates from customs tariffs, import duties and taxes.

Physical Progress in this month

- Excavation for 110k substation and OCC building completed.

- Pillar foundations completed

- Backfill sand has been approved by Engineer.

- Masonry brick has been approved by Engineer.

- Earthing material and calculation has been approved.

- Backfill work to level No.1 commenced

- Earthing work for earthing grid beneath ground level.

- Brick work to perimeter of substation building commenced.

- Physical Progress of Contractor Package V is shown in the Appendix V-6.

Activities for Coming Months

Permanent Works

- Finalize the foundation pillars

- Install the deep earth electrodes and pillar riser electrodes.

- Backfill the foundation base to the level for base of cable trenches.

- Installation of sub-foundation earthing grid.

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination