The report of 110kV overhead transmission line geological survey has been completed. The design for tower and foundation of overhead transmission line is under preparation. Two power transformers 110/22kV 10KVA were manufactured and successfully routine factory tested on July 15 and 16, 2002. The technical documents and quotation for connecting plan of 110/22kV substation to EVN power network has been submitted. The design of substation and tunnel control building has been completed and the construction of building foundation pillars is proceeding. The co-ordination meeting with Contractor of Package V were held from July 29 to August 3, 2002. Physical Progress in this month
Activities for Coming Months Permanent Works