Welcome to Our Site!
 

 

As of June 30, 2002

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Time Elapsed (days) 190 of 540 (35.19%)

Progress

 
110/22 kV Substation  
110 kV Transmission Line  

 

Photographs

 

Top

Construction Supervision

The Contractor has continued submission of manufacturer's list of proposed items; some items are still outstanding.

The Contractor has established a site office at the location of the Operation Building and has begun excavation work. The site has been fenced.

The 110kV Transmission Line Survey has been completed.

The volume of construction tasks completed, has not reached minimum payment level

Drawing approval for construction is continuing.

The Contractor has added List Key Staff

No equipment is as yet mobilized.

First materials on site, cement, bricks, rebars

No adverse weather influence has yet occurred.

Activities for Coming Months

Permanent Works

- Finalize the excavation work for 110.220kV Substation Operation Control Center Building.

- Formwork, Backfilling work, re-bar installation, concrete laying and earthing work.

- Continue the detailed design work on approved equipment type and manufacturer.

Temporary Works

- Site Workshop
Previous month / Next month

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination