Welcome to Our Site!
 

As of August 31, 2002

Physical Progress

Contractor

Matsushita - Itochu Consortium

Commencement of the Works

13 March 2002

Time Elapsed (days) 178 of 1080 (16.5%)

Progress

 
   
   

 

Photographs

Top

Construction Supervision

During the reporting period, the Contractor prepared the construction works as follows:

- Prepare technical information in accordance with the requirements raised during the coordination meeting held from July 29 to August 3, 2002.

- Study a modification of the water supply and water treatment system.

- Prepare drawings for ventilation system.

- Negotiate the conditions and technical specifications with sub-contractors.

- Prepare the mobilization and site establishment.

  • Construction schedule for Coming Month

Permanent work schedule

- Provide some technical information required during the coordination meetings held from July 29 to August 2, 2002.

- Provide proposal for modification of the existing water supply & water treatment system.

- Proceed with contract negotiation with the Vietnamese subcontractors

- Prepare for the next coordination meeting with PK1A, PK1B and PK5

- Study the coordination matters involved with a PK3 Contractor.

- Prepare the shop drawings for the ventilation equipment

- Prepare the mobilization and site establishment

- Prepare the details and schedule of O&M training

Temporary Work

- Apply for VAT code to Danang Tax Office

- Study the site office establishment and storage facilities

- Make up a Master List for the equipment to be imported to Vietnam.

Top

Previous month / Next month

This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination