Welcome to Our Site!
 

As of July 31, 2002

Physical Progress

Contractor

Matsushita - Itochu Consortium

Commencement of the Works

13 March 2002

Time Elapsed (days) 138 of 1080 (12.8%)

Progress

 
   
   

 

Photographs

Top

Construction Supervision

The Contractor prepared the construction works as follows:

- Executing a field study of high level reservoir, drill shaft site, water intake and water pipeline for the pump room.

- Making shop drawings for the ventilation equipment.

- Preparation of the mobilization and site establishment.

- Study the scope of works and general conditions for the subcontractors.

The Contractor also prepared the following documents during the reported month and these documents would be submitted in the beginning of August, 2002:

- Mobilization Program

- Staff Organization Plan

- Submittal Resister

- Quality Control Plan

- Environmental Control & Protection Program

- Safety Plan

  • Construction schedule for Coming Month

Permanent work schedule

- Prepare some technical information required during the coordination meetings held between Jul 29 and Aug. 2.

- Study the modification of the existing water supply and water treatment system.

- Review the BOQ Pay Items for the water related facilities and fire hydrant in comparison with the relevant drawings.

- Make shop drawings for the ventilation equipment.

- Prepare the mobilization and site establishment.

- Negotiate with Vietnamese Sub-contractor on scope of works and general conditions.

- Prepare details and schedule of O & M training.

Temporary Work

- Apply for VAT code to Danang Tax Office

- Make up a Master List for the equipment to be imported to Vietnam.

Top

Previous month / Next month

This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination