Progress Report > Package IV - Mechanical Works
The Contractor prepared the construction works as follows: - Executing a field study of high level reservoir, drill shaft site, water intake and water pipeline for the pump room. - Making shop drawings for the ventilation equipment. - Preparation of the mobilization and site establishment. - Study the scope of works and general conditions for the subcontractors. The Contractor also prepared the following documents during the reported month and these documents would be submitted in the beginning of August, 2002: - Mobilization Program - Staff Organization Plan - Submittal Resister - Quality Control Plan - Environmental Control & Protection Program - Safety
Plan
Permanent work schedule
Temporary Work