Progress Report > Package IIA - Lang Co Bridge Section
Substructure:
Superstructure:
Approach Road
Girder Production
Permanent Works
Three bored piling machines R-9G, TRC and Reffer are under the condition of operation. Three more bored piling machines GPS, Bawer and ED5500 are mobilizing and will commence to work soon. Pier No.9: 10 of 10 nos. of bored piling are finished and continue piling work. Pier No.14: 10 of 10 nos. of bored piling have been completed. Pier No.15: 5 of 12 nos. of bored piling are finished and continue piling work. Pier No.16: 3 nos. of piles were drilled but boulders are disturbing to continue drilling work. Contractor is preparing double casing method now. Pier No.17: 10 of 10 nos. of bored piling have been completed. Additional pile No.7' has constructed because Pile No.7 was rejected due to the result of working record and sonic test. Pier No.18: 12 of 12 nos. of bored piling have been completed. Pier No.19: 10 of 10 nos. of bored piling have been completed but No.6 pile is waiting for sonic test for approval because this pile had trouble at the concrete pouring time. Pier No.22: 5 of 9 nos. of bored piling are finished and continue piling work. Pier No.23: 9 of 9 nos. of bored piling have been completed.
Pier No.14: Sheet piling work has commenced and will continue excavation for footing. Pier No.17: Pier column is under construction of concrete work. Pier No.18: Concrete work has been completed up to cross head. Pier No.23: Excavation is finished and continue to footing concrete.
Superstructure work is not commenced yet.
North approach road is finished embankment up to 50,000m3 and continue. South approach road is finished embankment up to 1,000m3.
Production yard P19: 17 nos. of girder are finished production and will continue. Production yard A2: Preparation work has completed and commenced girder production.
Schedule has been revised by Contractor, but total schedule is 3 month behind at end of June 2002 based on the Clause 14.1 schedule. Following activities are delayed now.
Activities
for Coming Months
Construction
of P14: base, Pier shaft and cross head Bored pile of P15, P16, P22, P7, P8, P21 Construction P23: Pier base, pier column. PCI girder: 16 girders Construction of Northern Approach Construction of P9: completed pier base Construction P22: completed pier base Bored pile P24: Completed 3/6 piles d1500m
Construction of access road No.1 & No.2 This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team |
|
||||||||||||||||