As of May 31, 2002

Physical Progress

Contractor

JV of Thang Long and Truong Son

Commencement of the Works

1st July 2001

Time Elapsed (days) 335 of 900 (37.22%)
Progress  

North Approach

 

Lang Co Bridge (867m)

 

South Approach

 

 

Photographs

Lowering steel sheet pile at P14 - Footing construction
Construction of pier sharf P17
Construction of pier shaft and cross head P18
Pier P18 completed
Construction of bored pile P23
Finishing girder at casting yard No.1
Construction of North approach road
Casting girder 33m

 

 

Top

Construction Supervision

Summary 

Permanent Works

  • Lang Co Bridge

Pier No.14: Bored piling has completed.

Pier No.15: Bored piling is under construction.

Pier No.17: Bored piling has been completed and excavation has also completed. Footing concrete has been done.

Pier No.18: Concrete work of column has completed up to cross beam.

Pier No.19: Bored pile has completed but pile 6 is subject to the result of sonic testing.

Pier No.P23: 5 of 9 bored piles has completed.

  • PC girder casting yard
Beam production continue at production yard P19 and 10nos. of beam has finished of pre-stressing.
  • Pre-stress concrete girder work:

Completion of 07 girders including pre-stressing tension for girder.

Casting eighth girder concrete.

Preparation of form and reinforcement for ninth girder.

  • South Abutment

Clearing and Grabbing has completed.

Removing boulders for bored piling work has commenced toprepair.

  • Approach road work

Sand matting and embankment work have commenced.

Activities for Coming Months

  • Permanent Works:

 

  • Temporary Works:

Top

Previous month / Next month

This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team


 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination