Construction
Supervision
Summary
Completion
of 12 piles for Pier P18
Completion
of 9 piles for P19, one pile not constructed yet.
Completion
of 10 piles for P17, not including one pile more supplemented.
Completion
of 10 piles for P14, the sonic test has not yet implemented.
Completion
of 05 pile for P15, not including two piles of problem
Drilling
hole for first of Pier P16
Final
drilling hole for first pile of pier P23
Total
of completion pile: 46
Completion
of 270m3 concrete for pile cap of pier
P18
Pouring
192.6 m3 concrete for P18 column with high
20.27m (final).
Completion
of structure backfill of pier P18 foundation pile.
Completion
of pile sheet installation and excavation for pier
P17 pile cap construction.
Start
of chip-off of pile head of pier P17.
Completion
of 07 girders including pre-stressing tension for
girder.
Casting
eighth girder concrete.
Preparation
of form and reinforcement for ninth girder.
Fill
10,000m3 for North embankment.
Fill
1,000m3 for South embankment.
Completion
of plan and access road for construction of Pier P08
to P19 and pier P20 to abutment A2 (At somewhere used
mine explosive not completed yet)