As of April 30, 2002

Physical Progress

Contractor

JV of Thang Long and Truong Son

Commencement of the Works

1st July 2001

Time Elapsed (days) 305 of 900 (33.89%)
Progress  

North Approach

Sand matting has started

Lang Co Bridge (867m)

Piling for Pier No. 14, 15, 17 & 19. Concrete work for P18. Blasting work for boulders of P23

South Approach

Clearing and grabing completed

 

Photographs


Pouring concrete of bored pile P14

Granty crane

Lowering Steel sheet pile ate P17 - footing construction

Lowering Steel sheet pile ate P17 - footing construction

Construction of access road from P17 to P7

Pouring grout of duct Girder

Construction of pier column of P18

Pouring concrete of Girder 33m GLC3-01

Construction of girder 33m

Construction of column P18 pier

 

Top

Construction Supervision

Summary 

  • Pile Work: total 37 piles

Completion of 12 piles for Pier P18

Completion of 9 piles for P19, one pile not constructed yet.

Completion of 10 piles for P17, not including one pile more supplemented.

Completion of 10 piles for P14, the sonic test has not yet implemented.

Completion of 05 pile for P15, not including two piles of problem

Drilling hole for first of Pier P16

Final drilling hole for first pile of pier P23

Total of completion pile: 46

  • Pier Work

Completion of 270m3 concrete for pile cap of pier P18

Pouring 192.6 m3 concrete for P18 column with high 20.27m (final).

Completion of structure backfill of pier P18 foundation pile.

Completion of pile sheet installation and excavation for pier P17 pile cap construction.

Start of chip-off of pile head of pier P17.

  • Pre-stress concrete girder work:

Completion of 07 girders including pre-stressing tension for girder.

Casting eighth girder concrete.

Preparation of form and reinforcement for ninth girder.

  • Approach road work

Fill 10,000m3 for North embankment.

Fill 1,000m3 for South embankment.

  • Approach road work

Completion of plan and access road for construction of Pier P08 to P19 and pier P20 to abutment A2 (At somewhere used mine explosive not completed yet)

Activities for Coming Months

  • Permanent Works:

Construction P18: Pier head cross

Bored pile of P15, P16

Construction P19: Foundation Excavated, Pier base

PCI girder: 08 nos.

Construction of Northern approach

Construction of Southern approach road

  • Temporary Works:

Construction of access road No.1 & No.2

Top



This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team


 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination