As of July 31, 2002

Physical Progress

Contractor

JV of Thang Long and Truong Son

Commencement of the Works

1st July 2001

Time Elapsed (days) 396 of 900 (40.56%)
Progress  

North Approach

under construction

Lang Co Bridge (867m)

Bored Piling for P7, P9, P14, P17, P18, P19, P22 & P23 completed. Concrete Work for P7, P14, P22, P23.

South Approach

finished embankment

 

Photographs

General view of Construction site
Sheet pile driving at P7
Construction of P14' base
P17 & P18 have been completed
Construction of bored pile at P21
Construction of pier shaft P23
Construction of bored pile at P24
Girders on Site
Construction of North embankment

 

Top

Construction Supervision

Summary 

Bored Piling:

Pier 7, Pier 9, Pier 14, Pier 17, Pier 18, Pier 19, Pier 22, and Pier 23 are completed bored piling.

Total 95 nos. of bored piling are completed up to present.

Pier 8, Pier 12, Pier 15, Pier 16, Pier 21 and Pier 24 are under construction of bored piling.

Substructure:

Pier 17 and Pier 18 have been completed concrete works up to cross head.

Pier 7, Pier 14, Pier 22 and Pier No.23 are under construction of substructure

Superstructure:

Superstructure is not commenced yet.

Approach Road

North approach road is under construction and South approach road is finished embankment.

Girder Production

Two places of girder production yard P19 and A2 are under operation.

24 nos. of girders are completed of production.

Permanent Works

  • Bored Piling:

Six bored piling machines R-9G, TRC, Reffer, GPS, ED5500 and Bauer are mobilized to the site, and under the condition of operation.

Pier No.7: 8 of 8 nos. of bored piles have completed.

Pier No.8: 1 of 8 nos. of bored piles are finished and continue piling work.

Pier No.9: 10 of 10 nos. of bored piles have completed.

Pier No.12: 6 of 12 nos. of bored piles are finished and continue piling work.

Pier No.14: 10 of 10 nos. of bored piles have been completed.

Pier No.15: 5 of 12 nos. of bored piles are finished and continue piling work.

Pier No.16: 3 nos. of piles were drilled but it was impossible to continue drilling because met the boulders.

Contractor is preparing double casing method now.

Pier No.17: 10 of 10 nos. of bored piles have been completed.

Additional pile No.7' has constructed because Pile No.7 was rejected due to the result of working record and sonic test.

Pier No.18: 12 of 12 nos. of bored piles have been completed.

Pier No.19: 10 of 10 nos. of bored piles have been completed but No.6 pile is waiting for sonic test for approval because this pile had trouble at the concrete pouring time.

Pier No.21: 3 of 12 nos. of bored piles are finished and continue piling work.

Pier No.22: 9 of 9 nos. of bored piles have been completed.

Pier No.23: 9 of 9 nos. of bored piles have been completed.

Pier No.24: 2 of 6 nos. of bored piles are finished and continue piling work.

  • Substructure:

Pier No.7: Sheet piling work has commenced but it has met boulders during sheet pile driving.

Pier No.14: Footing concrete has completed and continuing column concrete work.

Pier No.17: Concrete work has been completed up to cross head.

Pier No.18: Concrete work has been completed up to cross head.

Pier No.22: Excavation work is carrying on.

Pier No.23: Footing concrete has completed and continuing column concrete work.

  • Superstructure:

Superstructure work is not commenced yet.

  • Approach Road

North approach road is finished embankment up to 50,000m3 and continue.

South approach road is finished embankment up to 1,000m3.

  • Girder Production

Production yard P19: 17 nos. of girder are finished production and will continue.

Production yard A2: 3 nos. of girder are finished production and will continue.

  • Schedule overview

Schedule has been revised by Contractor, but total schedule is 3.5 month behind at end of July 2002 based on the Clause 14.1 schedule.

Three critical paths are running on the schedule now.

CP1: A1 - P1 - P2 - Launching from A1 is 103 days behind at the end of July 2002.

CP2: P8 - P10 - P3 - P4 - P5 -P6 is 51 days behind.

CP3: P24 - A2 - P25 - Launching from A2 is 26 days behind.

Activities on the CP1 has no action at this moment, therefore schedule is delaying day by day. There is potential to delay more in future. Counter measure for this critical path is required urgently.

P24 of CP3 has met boulders during pile driving time and it takes more times than expected.

This critical path has also potential to delay. We are close watching about progress.

Construction method of Pier No.1 to Pier No.6 has agreed to change from floating method to island method at the technical meeting with PMU 85 in May 2002.

Activities for Coming Months
  • Permanent Works:

 

  • Temporary Works:

 

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination