Progress Report > Package IIA - Lang Co Bridge Section
Substructure:
Superstructure:
Approach Road
Girder Production
Permanent Works
Six bored piling machines R-9G, TRC, Reffer, GPS, ED5500 and Bauer are mobilized to the site, and under the condition of operation. Pier No.7: 8 of 8 nos. of bored piles have completed. Pier No.8: 1 of 8 nos. of bored piles are finished and continue piling work. Pier No.9: 10 of 10 nos. of bored piles have completed. Pier No.12: 6 of 12 nos. of bored piles are finished and continue piling work. Pier No.14: 10 of 10 nos. of bored piles have been completed. Pier No.15: 5 of 12 nos. of bored piles are finished and continue piling work. Pier No.16: 3 nos. of piles were drilled but it was impossible to continue drilling because met the boulders.
Pier No.17: 10 of 10 nos. of bored piles have been completed.
Pier No.18: 12 of 12 nos. of bored piles have been completed. Pier No.19: 10 of 10 nos. of bored piles have been completed but No.6 pile is waiting for sonic test for approval because this pile had trouble at the concrete pouring time. Pier No.21: 3 of 12 nos. of bored piles are finished and continue piling work. Pier No.22: 9 of 9 nos. of bored piles have been completed. Pier No.23: 9 of 9 nos. of bored piles have been completed. Pier
No.24: 2 of 6 nos. of bored piles are finished and continue
piling work.
Pier No.7: Sheet piling work has commenced but it has met boulders during sheet pile driving. Pier No.14: Footing concrete has completed and continuing column concrete work. Pier No.17: Concrete work has been completed up to cross head. Pier No.18: Concrete work has been completed up to cross head. Pier No.22: Excavation work is carrying on. Pier
No.23: Footing concrete has completed and continuing
column concrete work.
Superstructure work is not commenced yet.
North approach road is finished embankment up to 50,000m3 and continue. South approach road is finished embankment up to 1,000m3.
Production yard P19: 17 nos. of girder are finished production and will continue. Production yard A2: 3 nos. of girder are finished production and will continue.
Schedule has been revised by Contractor, but total schedule is 3.5 month behind at end of July 2002 based on the Clause 14.1 schedule. Three critical paths are running on the schedule now.
Activities on the CP1 has no action at this moment, therefore schedule is delaying day by day. There is potential to delay more in future. Counter measure for this critical path is required urgently. P24 of CP3 has met boulders during pile driving time and it takes more times than expected. This critical path has also potential to delay. We are close watching about progress. Construction
method of Pier No.1 to Pier No.6 has agreed to change
from floating method to island method at the technical
meeting with PMU 85 in May 2002. Activities
for Coming Months
This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team |
|
||||||||||||||||