Progress Report > Package III - Electrical Works

As of April 30, 2005

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Commencement of the Works

14 February 2003

Contract Period 26 months (Until April 13, 2005)
Time Elapsed (days)  797 of 780 (102.18%) Remaining 45 days

Progress

 

Mainly system commissioning

Photographs

MV cabling for South Road & Bridge
MV Cabling Joint work for South Road
Trench Excavation at South Road
FOC joint work at South Road
Compact substation at S/S 7
MT Lighting check
MT Lighting check
MT Lighting Check
ET Lighting Check
VMS Installation at North Portal
Traffic Sign at North Portal
Emergency Phone Installation at Niches
Camera Installation at MT
Earthing work at VAB

Top

Construction Supervision

Summary from Contractor

The month of April saw major progress, as expected, in the testing and pre-commissioning of power, CCTV, telecommunications, fire alarm and detection, and traffic control system. Testing was ongoing while final installations of parts of these systems were being completed. This included OCC control room equipment and workstation connections and use and installation and commissioning of the VDU. Over all commissioning by ABB was at approximately 50% at end of April.

All main tunnel and evacuation tunnel lighting was operational from local control by late April.

The Contractor continued with installation works that should have been finished months ago at STP and NTP and in VMB. All substations except S/S#8 at STP were energised by end of April. The MV, fibre optic and road lighting cables were installed along the south road after months of delay in slow excavation of the cable trench.

On site training began in April with HAMADECO staff assigned to accompany PKIII trainers during field final installations and checking.

Installation of road lighting poles and luminaires along the south road and connections was almost completed as was the last road lights from NTP to Highway 1.

Final assembly of the Radio Rebroadcast system was ongoing in Belgium and FAT is expected in May.  Completion of installation works continues for parts of CCTV, traffic control, telephone, and for general electrical works.  PKIII have scheduled 1 month for completion of RRB in June. Main panel hardware and antenna mast has not yet been delivered. 

Physical Progress in this month

Completion of installation and testing of MV cable and fibre optic cable along south road (OCC to STP).  The last 400m of MV cable for second feeder to S/S#6 from S/S#3 was installed, tested and energised. This was missing because of Contractors errors in MV cable quantity order.

Installation of GIS, distribution transformers, main LV switchboard, UPS, battery systems, and all other major items installation completed in all substations.

Traffic control system loop detector installation with installation and connection of feeder cables was for loops inside walkway was completed.

Installation of the fire detection fibre optic cable sensor in the MT was completed. Installation of manual push button at fire hydrant niches began and was 90% complete

Installation of the radio rebroadcast leaky coaxial antenna in the tunnel continued but is not complete.

Installation of CCTV cameras and associated connection boxes was mainly carried out in April but 9 units remained at month’s end.

Excavation of trench for MV, LV, and fibre optic cable along the south road continues and was nearing completion at the end of February.  Road lighting poles and luminaires 90% completed along north and south roads and bridges.

Various cable ladder and small power and lighting installations in tunnel and VAB were being completed. Fire resistant (FR) cable joint kits were delivered and installed in FR cables in the tunnel.

Top

Previous month/Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination