Welcome to Our Site!
 

 

As of October 31,2004 

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Commencement of the Works

21 December 2001

Contract period

540 days (Until June 20, 2003)

Time Elapsed (days)

1000 of 540 (185.18%) Extended from June 20, 2003

Progress

 

 

Completed

Photographs

Top

Construction Supervision

A major milestone was achieved with the energising of the transmission line and Hai Van high voltage substation on the 30 June for a successful 72 hour test energisation. Over the 72 hour period the 110kV GIS, 22kV GIS, the main power and auxiliary transformers were energised from Lien Chieu substation. The operation and synchronisation of the diesel generators to the grid was also demonstrated. The synchronising of the generators with the network when the network is re-energised after an outage is still to be done. It requires switching on and off and on again of the 110kV transmission line.

Snag lists of items to be adjusted, re-set or otherwise corrected were prepared in coordination with Engineer, PTC No. 2 and Load Dispatch Centre (A3). By the end of July all items had been cleared with the exception of CBFP relaying to be reset in Lien Chieu substation when another shut down can be arranged and synchronising of the generators to the network when generators are running. A important item that was outstanding was the transmission line differential protection inter-tripping and that was successfully completed on 1 August.

Contractor completed and delivered all the As- Built documentation required by contract in July. This included as-built drawings, and Operations and Maintenance manuals.

Permanent energisation (power supply) service will be carried out when a number of issues relating to operations and contract to pay for power consumption are resolved. It is intended to have the Hai Van substation permanently energised as soon as possible. SITOC inspection was carried out before and during test energisation.

On Site Training was provided by the Contractors staff from 14th to the 26th June at the OCC.   The approved courses covered all the PKV works including 110kV GIS, 22kV GIS, LV equipment, diesel generators and MicroSCADA

Problems Areas and Measures

The main problem area in July has been delays in getting permission for energizing the 110kV transmission line so that snag list items could be checked and the diesel generator auto synchronising operations with network re-energisation checked. It is necessary to re-energise to carry out checks and if necessary to re-energise each day for several days to resolve problems without waiting for 1 to 2 weeks between tests. 

A relay hardware problem prevented completion of the CBFP (circuit breaker failure protection) item during a 1 August shut down at Lien Chieu substation and another shutdown is required. A internal panel adjustment was required for generator network synchronising and re-testing requires energising of the 110kV line and switching sequences in cooperation with A3.

Activities for Coming Months

Completion of testing of CBFP in Lien Chieu and generator network synchronising when PTC No.2 and A3 can provide shutdowns and re-energisations of the transmission line.

Complete outstanding items of supply spare parts and tools.. Most are on site and have been turned over.

Major Events and Issues

The major event was the signing of the Final Turning-Over certificate including V.O. No. 1 works.

Final items on the snag list require cooperation and coordination with A3 and PTC2 for Lien Chieu shutdown and Hai Van substation reenergisation.

Issues remain on contracts resolution between HAMADECO and PTC No. 2 to operate the 110kV substation, and on a contract for HAMADECO (or some other responsible party) to pay for power used after permanent energisation. These are not PKV issues or responsibility as the PKV works have been successfully energised and tested.

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination